Financial Studies: Related to socioeconomic and monetary issues. (next 4 study titles below)

  1. Economic Impact of Parking Policy Options 1986 - Conducted for the Miami Downtown Development Authority's Parking Task Force to present a summary evaluation of the economic impact of recommended parking policy alternatives for downtown Miami. Completed October 1986. Work by Zuchelli, Hunter & Associates. Download the Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  2. Effects of Transportation Plan Development on Minority and Impoverished Urban Communities 1998 - Conducted for the University of South Florida (USF) to determine the effects of the transportation plan on minorities and impoverished urban communities. Work by Beverly G. Ward and Eric T. Hill. Download the Final Report via MetroNet. Or visit our office to view or get a copy of the report. Contact Elizabeth Rockwell at 305-375-4507 for complete details.
  3. Transportation Financial Analyses and Assessments Study 1997 - This study addresses the process in Miami-Dade County that leads to fundamental decisions about which transportation projects are implemented, the manner and sequential order in which they are implemented and the structuring of funding and financing of these projects. Work by KPMG. Download the Executive Summary, July 1997. Contact Carlos Roa at 305-375-4507 for complete details.
  4. Welfare to Work: Transportation Issues and Opportunities in Miami-Dade County 1998 - The main purpose of this study was to compile basic information concerning welfare recipients in Miami-Dade County who were eligible for the Work and Gain Economic Self-Sufficiency (WAGES) Program. Completed in December 1998. Work by FIU Metropolitan Center. Download the Final Report. Contact Elizabeth Rockwell at 305-375-4507 for complete details.

Freight Studies: Looking into cargo movement and truck traffic. (next 12 study titles below)

  1. Central Dade Transport Zone Study 2007 - This study looks at upgrading the infrastructure along the Miami River, Miami International Airport, the FEC Rail Yard, the Warehouse District, the Free-Trade Zone and look at expansion of road facilities throughout the district. Started September 2007 and completion August 2008. Work by Kimley-Horn & Associates. The approximately cost was $80,000. Download the Executive Summary and Final Report. Contact Larry Foutz at 305-375-4507 for complete details.
  2. Comprehensive Parking Study for Freight Transport in Miami-Dade County Study 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. The budgeted cost is approximately $65,000. STATUS: General Planning Consultant (GPC) to be selected. Contact Larry Foutz at 305-375-4507 for complete details.
  3. CSX Corridor Evaluation Study 2008 - ONGOING. This study will evaluate the feasibility of re-directing rail freight traffic outside the urbanized Kendall area and examine various concepts to introduce rapid transit service along the CSX rail corridors south of the Oleander Junction. Started July 2008. Expected completion was March 2009. Work by Parsons Transportation Group. The budgeted cost is approximately $138,500. Download the Presentation of January 27, 2009. STATUS: 85% complete. Contact Wilson Fernandez at 305-375-4507 for complete details.
  4. Freight Movement Study 1996 - Review assumptions made in the original Freight Movement Study concerning trucks and surface freight movement in the MPO's urban area travel model; review the status of recommendations made in the original study; investigate how e-business affects local area freight movement; and reestablish the Freight Transportation Advisory Committee (FTAC). Completed in December 1996. Work by The Corradino Group. Download the Executive Summary. Download the Final Report via MetroNet. Or visit our office to view or get a copy of the report. Contact Larry Foutz at 305-375-4507 for complete details.

  5. Miami-Dade Freight Plan 2007 - The objective of this study is to develop a freight master plan that will feed projects into the Long Range Transportation Plan. Started September 2007 and completed September 2008. Work by Gannett Fleming. The approximate cost was $124,929. Download the Executive Summary and Final Report. Contact Larry Foutz at 305-375-4507 for complete details.

  6. Port of Miami City Street Improvements 2000 - Also known as Seaport Truck Study. This study evaluated existing truck traffic movement in and out of the seaport and recommend alternatives to improve mobility within the downtown area. Completed September 2000. Work by Beiswenger Hoch & Associates. Download the Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.

  7. Port of Miami Freight Access Study 2006 - Evaluate a variety of intermodal alternatives for improving freight access to and from the Port of Miami. Studied from April 2006 to February 2007. Work by Cambridge Systematics. Download the Draft Executive Summary and Final Report. Contact Larry Foutz at 305-375-4507 for complete details.

  8. Railroad Rights-Of-Way Assessment Study 1993 - This study would create an inventory of all railroads in Miami-Dade County; examine for potential use in public transportation; and develop recommendations for particular corridors to be studied in detail. Completed August 1993. Work by ICF Kaiser Engineers. Please visit our office to view or receive a copy of this report. Contact Larry Foutz at 305-375-4507 for complete details.

  9. Regional Freight Plan 2008 - ONGOING. This study will analyze existing and new data and, in conjunction with the regional visioning process, develop a regional freight strategy and make implementation recommendations. Expected completion is December 2009. Started in May 2008. Work by Kimley-Horn & Associates (via FDOT). The approximate cost is $33,000 (the MPO's share of a tri-regional effort totaling $198,791). STATUS: 95% complete. Contact Larry Foutz at 305-375-4507 for complete details.

  10. Short Range Truck Traffic Study for the Airport West Area 2002 - Develop a set of standards and an implementation plan to better accommodate truck traffic and commercial truckers needs in the Airport West area. Completed in July 2002. Work by David Plummer & Associates. Download the Executive Summary, Final Report, and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.

  11. Trends in Heavy Truck Traffic Management Study 2003 - This study will research current trends in the management of such heavy truck traffic in major metropolitan areas to see what approaches work best to reduce motorists’ concerns while maintaining the flow of goods and services. Two freight and trucking-oriented studies have been previously conducted. The main focus was not on specifics of heavy truck operations on expressways and major arterials. Started June 2003 and completed October 2004. Work by Cambridge Systematics. Download the Executive Summary, Final Report, and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.

  12. Truck Route System for Miami-Dade County 2006 - It's task was to identify current and future corridors for heavy truck traffic and to preserve roadways for such vehicles by designating them as truck routes. Started August 2006 and completed June 2007. Work by The Corradino Group. The approximate cost was $53,000. Download the Executive Summary and Final Report. Contact Larry Foutz at 305-375-4507 for complete details.

Maritime Studies: Related to water transit and waterways. (next 2 study titles below)

  1. Development of a Service Plan for Waterborne Transportation Services in Miami-Dade County 2004 - This study would develop a water transit service plan that would offer alternatives to local commuters driving single occupant private automobiles, and provide viable and attractive mobility options for visitors. Completed January 2005. Work by Kimley-Horn & Associates. Download the Executive Summary, Final Report, Presentation, and Water Transit Service Executive Summary Report (March 2007). Contact Jesus Guerra at 305-375-4507 for complete details.
  2. Feasibility of Utilizing Miami-Dade County Waterways for Urban Commuter Travel 2002 - This study assesses the feasibility of using the existing waterways within the Urban Growth Boundary of Miami-Dade County for commuter travel. Completed January 2003. Work by Gannett Fleming. Download the Final Report of January 8, 2003. Contact David Henderson at 305-375-1647 for complete details.

Non-motorized Studies: About bicycles and pedestrians and facilities for both. (next 45 study titles below)

  1. 107th Avenue Pedestrian and Transit Greenways Corridor Study 2002 - Explore the construction of a pedestrian transit greenway along 107th avenue from Flagler Street to SW 8th Street, in the City of Sweetwater. Started December 2002 and completed August 2003. Work by Florida International University. Download the Final Report. Contact David Henderson at 305-375-1647 for complete details.
  2. Automated Bicycle Rental System and Parking Plan 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. The budgeted cost is approximately $55,000. STATUS: General Planning Consultants (GPC) to be selected. (October 2009) Contact David Henderson at 305-375-1647 for complete details.
  3. Bay Harbor Islands Pedestrian and Bicycle Master Plan 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by the Town of Bay Harbor Islands. The budgeted cost is $18,665. STATUS: Pending contract negotiation. (October 2009) Contact Larry Foutz at 305-375-4507 for complete details.
  4. Bicycle/Pedestrian Mobility Plan for the Miami Downtown Development Authority 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. The budgeted cost is approximately $60,000. STATUS: General Planning Consultant (GPC) to be selected. (October 2009) Contact David Henderson at 305-375-1647 for complete details.
  5. Bicycle/Pedestrian Plan Update 2007 - ONGOING. This will prepare an update to the MPO’s Bicycle and Pedestrian plans including a vision, measurable goals and objectives, long range element and short range element. Topics include on- and off-road networks, prioritized pavement and trail projects, bike parking, Bike & Ride, safe routes to school, municipal coordination, encouragement and safety. Started in September 2007. Expected completion was October 2008. Work by Gannett Fleming. The budgeted cost is $98,711. Contact David Henderson at 305-375-1647 for complete details.
  6. Bicycle and Pedestrian Traffic Count Program 2006 - Provide information on the current usage of bicycling and walking at selected locations around the county for use in identifying and prioritizing improvements, performing “before-and-after” evaluations of programs and facilities and provide a baseline to monitor long-term trends. Started August 2006 and completed May 2008. Work by David Plummer & Associates. The approximate cost was $64,075. Download the Report. Contact David Henderson at 305-375-1647 for complete details.
  7. Bicycle Boulevard Planning Study 2009 - ONGOING. This study will look at ways to improve conditions for bicycling through the development of “bicycle boulevards” within the county. Started December 2008. Expected completion was October 2009. Work by Kimley-Horn & Associates. The budgeted cost is approximately $85,000. Contact David Henderson at 305-375-1647 for complete details.
  8. Bicycle Facilities Plan 1997 - The plan examined existing roadway conditions relating to bicycle travel and proposed a set of improvements of both on- and off-road facilities to incorporate into the TIP. Completed in 1997. Work by Barton-Aschman Associates. Download the Executive Summary. Contact David Henderson at 305-375-1647 for complete details.
  9. Bicycle Parking Plan for Miami-Dade Transit 2002 - The purpose of this study was to develop recommendations for new and improved bicycle parking facilities at Miami-Dade Transit Metrorail stations, park-and-ride lots and other transit hubs. Started in 2002. Work by by Center for Urban Transportation Research (CUTR) of the University of South Florida. Download the Final Report and Presentation. RESULTS: Phase 1 racks installed in 2006 (Dadeland South – Earlington Heights Metrorail Stations). Phase 2 racks (Brownsville-Palmetto Stations and other transit hubs) to be installed in Fall, 2008. Phase 3 (bike locker replacement in Winter, 2009). Contact David Henderson at 305-375-1647 for complete details.
  10. Bicycle Project Feasibility Evaluation 2003 - This study (Work Order No. GPC11-02) was to evaluate seven high-priority bicycle project through Miami-Dade County: the Commodore, Bird Road, NW 11th Street, Palm Avenue, Red Road, North Federal Highway, and M-Path trails. Started August 2003 and completed March 2004. Work by Kimley-Horn & Associates. Download the Final Report of November 19, 2003. RESULTS: Under design. $1 million programmed for design and construction in fiscal years 2008-2010 (GOB #127). Public workshop on design scheduled for 6/30. Contact David Henderson at 305-375-1647 for complete details.
  11. Bicycle Safety Education Program 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by University of Miami. The budgeted cost is approximately $50,000. STATUS: Pending contract negotiation. (October 2009) Contact David Henderson at 305-375-1647 for complete details.
  12. Bicycle Safety Program Plan - This study used Pedestrian and Bicycle Crash Analysis Tool (PBCAT) software developed for the Federal Highway Administration (FHWA) to identify common crash types occurring at locations throughout the County and develop countermeasures to address the same. Completed March 2006. Work by Cambridge Systematics. Download the Executive Summary and Final Report. RESULTS: "Share the Road" and "Steer Clear" public information material distributed. Washington Ave shared-use lane marking evaluation underway by Miami Beach. Contact David Henderson at 305-375-1647 for complete details.
  13. Bikes-on-Bus Service Delivery in Dade County Study 1995 - The purpose of this study was to determine how a bike-on-bus program for Dade County can enhance transit service and to identify ways to make such a program successful and efficient. Please visit our office to view or receive a copy of the Suitability and Feasibility Report, April 1995. Contact David Henderson at 305-375-1647 for complete details.
  14. Black Creek Trail Segment B Study 2006 - Complete a feasibility and planning study to develop a single non-motorized multi-use trail and linear park for "Segment B" within the right-of-way along Black Creek Canal. Started August 2006 and completed October 2007. Work by Kimley-Horn & Associates. The approximate cost was $56,000. Download the Executive Summary and Final Report. RESULTS: $900,000 programmed for construction in fiscal year 2011 (FM #4209161). Contact David Henderson at 305-375-1647 for complete details.
  15. City of North Miami Beach Pedestrian & Bicycle Safety Analysis Study 2004 - This study lays the groundwork for a network of trails and bikeways in North Miami Beach, including the existing Snake Creek Trail. Studied from March 2004 to December 2004. Work by Dover, Kohl and Partners (under contract to the City of North Miami Beach). Download the Final Report. Contact David Henderson at 305-375-1647 for complete details.
  16. City of North Miami Beach Pedestrian/Bicycle Safety Study 2007 - This study focuses on the intersection of SR-826/NE 163rd Street and US-5/US1 (Biscayne Boulevard) upon the request of the City of North Miami Beach. Started October 2007 and completed September 2008. Work by URS Corporation. Download the Report. Contact David Henderson at 305-375-1647 for complete details.
  17. City of North Miami Bike, Park and Ride Study 2007 - Formerly called North Miami Bicycle Parking and Transit Circulator Feasibility Study. This will complete a comprehensive bicycle planning and transit circulator feasibility study to provide better bicycle facilities and identify strategies that will create greater connectivity between bicycle and public transit systems. Started October 2007 and completed June 2009. Work by the City of North Miami and Kimley-Horn & Associates. The approximate cost was $55,258 as part of the Municipal Grant Program. Download the Final Report and Presentation. Contact David Henderson at 305-375-1647 for complete details.
  18. City of South Miami US-1 Pedestrian Overpass Study 2000 - Completed by McHarry Associates. Investigate and document the potential locations and configurations for a pedestrian overpass across US-1 (South Dixie Highway). Please visit our office to view or receive a copy of this report. Contact David Henderson at 305-375-1647 for complete details.
  19. City of Sunny Isles Bridge to Link a Pedestrian/Bicycle Greenway Study 2003 - Sunny Isles Bridge to Link a Pedestrian/Bicycle Greenway on North Bay Road at NE 172 Street. Studied from December 2003 to December 2004. Work by Calvin Giordano & Associates (under contract with the City of Sunny Isles Beach). Download the Final Report. Contact David Henderson at 305-375-1647 for complete details.
  20. Civic Center TMO Commuter Characteristics Study 1994 - This study's main purpose was to investigate current pedestrian activities within the Civic Center area and to develop a Pedestrian Amenities Plan. This plan included safety issues that were also addressed in the plan. Completed in December 1997. Work by Center for Urban Transportation Research (CUTR) of the University of South Florida. Download the Executive Summary. Download the Report via MetroNet, or visit our office to view or get a copy of the report. Contact Jesus Guerra at 305-375-4507 for complete details.
  21. Civic Center TMO Pedestrian Amenities and Safety Study - To identify travel characteristics of employees, students, and visitors in the Civic Center area, locate transportation facilities within the area, develop a commuter characteristics data file, and prepare an action plan to implement short and long term TDM strategies. Work by Barton-Aschman Associates. Please visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.
  22. Dadeland Regional Activity Center Study 1997 - The objective of this study is to develop a set of planning activities to be implemented for improving mobility in the Dadeland Regional Activity Center area. Download the Final Report and Implementation Measure Report. Contact Susan Schreiber at 305-375-4507 for complete details.
  23. Ludlam Trail Non-Motorized Corridor Planning Environmental Study 2003 - The Ludlam Trail is a non-motorized transportation route through the county's urban core, expanding the traveler’s transportation options, enhancing the quality of life, and reducing single-occupant automobiles. Running northward from Dadeland North Metrorail Station to NW 12th Street/Perimeter Road next to MIA, it is 7 miles along the FEC Railway parallel to and west of Ludlam Road/67th Ave. Completed in March 2003. Work by Reynolds, Smith & Hills, Inc. Download the Final Report. Contact David Henderson at 305-375-1647 for complete details.
  24. Metrorail M-Path Master Plan 2006 - It addresses operational issues and problem areas within the M-Path bicycle/pedestrian corridor originally created in 1983. The corridor runs from the Miami River to SW 67th Avenue along US-1 (South Dixie Highway). Started August 2006 and completed July 2007. Performed by Kimley-Horn & Associates. The approximate cost was $55,000. Download the Executive Summary and Final Report. RESULTS: $1.7 million of GOB and FTA funds available in current year for design and construction of recommended improvements. Project management to be coordinated by CMO. Contact David Henderson at 305-375-1647 for complete details.
  25. Metropolitan Dade County Comprehensive Bicycle Plan 1986 - Identifies projects and strategies to meet the most pressing needs of bicyclists in the urban area. This plan represents the first major planning effort addressing needed bicycling-related improvements in Dade County since the publication of the 1972 Dade County Bikeways Plan. Download the Comprehensive Bicycle Plan via MetroNet, or visit our office to view or receive a copy of this report. Contact David Henderson at 305-375-1647 for complete details.
  26. Miami-Dade County Bicycle and Pedestrian Facility Maintenance Program 2008 - ONGOING. It's to develop a comprehensive maintenance program to ensure the longevity and safety of greenway trails within the county. Started in December 2008. Expected completion was September 2009. Work by Florida International University. The approximately cost $80,000. STATUS: 70% complete. Contact David Henderson at 305-375-1647 for complete details.
  27. Miami-Dade Most Dangerous Locations for Elderly Pedestrians 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by Miami-Dade Public Works and Florida International University. The budgeted cost is approximately $67,000. STATUS: Pending contract negotiation. (October 2009) Contact David Henderson at 305-375-1647 for complete details.
  28. North Dade Greenways Master Plan 1997 - To provide an integrated system of connectors for cyclists, joggers, equestrians, and pedestrians along more than 300 miles of urban corridors. It will also seek to reconstruct formerly connected landscapes and create new ecological corridors among them. This landscape reconciliation will provide a variety of recreational experiences within an ecologically driven area. Completed December 1997. Work by Florida International University. Download the Executive Summary and Final Report. Contact David Henderson at 305-375-1647 for complete details.
  29. Online Safe Routes to School Pilot Program 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by Florida International University. The budgeted cost is approximately $75,000. STATUS: Pending contract negotiation. (October 2009) Contact David Henderson at 305-375-1647 for complete details.
  30. Pedestrian Safety at Miami-Dade Regional Parks Study 2009 - ONGOING. A description of this study is forthcoming. Started in May 2009. Expected completion is January 2010. Work by David Plummer & Associates. The cost is $56,496. STATUS: 25% complete. Contact David Henderson at 305-375-1647 for complete details.
  31. Pedestrian/Bicycle Safety Study 2007 - ONGOING. This study will document existing traffic operations conditions and alternative modes of transportation (bus transit, pedestrian ways, bicycle connections, etc.) at NE 163rd Street and Biscayne Boulevard; and develop feasible alternatives. Started October 2007. Expected completion was September 2008. Work by the City of North Miami Beach. The projected cost is approximately $20,000. Contact David Henderson at 305-375-1647 for complete details.
  32. Rail Convertibility Study 2003 - Also called Rails to Trails; or Converting Rails to Transit, Bike & Pedestrian Facilities Study. This study will provide a comprehensive assessment of abandoned and underutilized rail right-of-way for potential public transportation uses. Previous related work can be found in the Railroad Rights-of-Way Assessment Study (1993). Started October 2003 and completed September 2004. Work by The Corradino Group. Download the Final Report, November 2004. Contact Wilson Fernandez at 305-375-4507 for complete details.
  33. Safe Routes to School Program Study 2003 - To identify and propose corrective measures on existing student pedestrian safety hazards along designated Safe Routes to School in selected high student pedestrian crash areas. An existing Safe Routes to School Program is in place, but has not been updated for several years. Started April 2003 and completed September 2006. Work by Reynolds, Smith & Hills, Inc. Download the Executive Summary, Presentation, and Technical Memorandum No. 3. Contact David Henderson at 305-375-1647 for complete details.
  34. Safe Routes to School Program Study 2006 - This would prepare “safe routes to school” plans for elementary schools that identify a safe route and infrastructure improvements within the attendance boundary. Completed July 2007. Work by Reynolds, Smith & Hills, Inc. The approximate cost was $60,000. Download the District-wide Traffic Operations Studies No. 25 and District-wide Traffic Operations Studies No. 26. RESULTS: $2.2 million programmed for design and construction of 15 Liberty City-area elementary schools in the current year (FM #4208811). Contact David Henderson at 305-375-1647 for complete details.
  35. Safe Routes to School Program Study 2007 - This would prepare “safe routes to school” plans for elementary schools that identify a safe route and infrastructure improvements within the attendance boundary. Started in October 2007 and completed in July 2008. Work by The Corradino Group. The approximate cost was $55,000. Download the Report. Contact David Henderson at 305-375-1647 for complete details.
  36. Safe Routes to School Program Study 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by the Village of Palmetto Bay. The budgeted cost is approximately $40,000. STATUS: Pending contract negotiation. (October 2009) Contact David Henderson at 305-375-1647 for complete details.
  37. Senior High School Student Safety Campaign 2008 - ONGOING. This study will develop a student pedestrian and vehicular safety campaign program targeting senior high school students. Started November 2008. Expected completion was June 2009. Work by Miami-Dade County Public Schools. The approximate cost is $25,000. STATUS: 90% complete. Contact David Henderson at 305-375-1647 for complete details.
  38. School Zone Traffic Congestion Study 2002 - Study the alternatives for transportation operations and design for improved access and area traffic flow surrounding public schools. Completed in July 2002. Work by David Plummer & Associates. Download the Executive Summary, Final Report, and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.
  39. Snake Creek Bike Trail Planning and Feasibility Study 2004 - Formerly Snake Creek Canal Bikeway Planning and Feasibility Study. This study will plan for two segments of a non-motorized trail within the Snake Creek canal right-of-way. A portion contains the Snake Creek Bike Path and will look at expanding the bike path to connect similar facilities in North Miami Beach and the proposed Florida Turnpike greenway. Started August 2004 and completed June 2005. Work by Kimley-Horn & Associates. Download the Final Report. RESULTS: $3.7 million programmed for design and construction in fiscal years 2010-2012 (FM #2512003). Contact David Henderson at 305-375-1647 for complete details.
  40. Snapper Creek Trail Segment A 2007 - This study will help establish ways to bring the existing trail up to current standards for amenities and crossings safety, improve access, and determine best side of canal for new trail portions where needed. Started July 2007 and completed March 2009. Expected completion was August 2008. Work by Kimley-Horn & Associates. The approximate cost was $55,000. STATUS: Awaiting final report. Contact David Henderson at 305-375-1647 for complete details.
  41. South Beach Bicycle and Pedestrian Study 1994 - Work by Barton-Aschman Associates. Undertaken as part of the MPO’s assistance to the South Beach Transportation Management Association. The traditional grid roadway system, high percentage of recreational trips, parking demand, short trip distances, extensive transit services and low income employment are ideal for promoting programs to encourage cycling and walking. Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact David Henderson at 305-375-1647 for complete details.
  42. South Dade Greenway Network Master Plan 1994 - Out of the chaos of Hurricane Andrew, a community desire emerged to create a comprehensive system of multi-purpose trails in South Dade County that would provide scenic, recreational and utilitarian corridors to be enjoyed by both residents and visitors. Completed in 1994. Work by The Redland Conservancy. Download the Final Report. Contact David Henderson at 305-375-1647 for complete details.
  43. Traffic Calming for Pedestrians at Miami-Dade Community College Wolfson Campus Study 2003 - Pedestrian-oriented traffic calming and mitigation study of the area adjacent to and surrounding the downtown Wolfson campus of Miami-Dade College including mitigating car and truck traffic impacts accessing the Port of Miami and downtown Miami. Started November 2003 and completed June 2004. Work by HDR, Inc. Download the Executive Summary, Final Report, and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.
  44. Village of Palmetto Bay Bicycle and Pedestrian Master Plan 2008 - It's objective is to create a vision of non-motorized transportation within Palmetto Bay boundaries. Started November 2008 and completed June 2009. Work by the Village of Palmetto Bay. The approximate cost was $50,000. Download the Master Plan. Contact David Henderson at 305-375-1647 for complete details.
  45. Web-based Bicycle Route Planning Tool 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by the Florida International University. The approximate cost was $50,000. STATUS: Pending contract negotiation. (October 2009) Contact David Henderson at 305-375-1647 for complete details.

Outreach Studies: Related to public involvement and education. (next 7 study titles below)

  1. Aesthetic Guidelines for Transportation Projects in Miami-Dade County 2009 - PENDING. Develop a set of countywide aesthetic guidelines and best practices to assist transportation agencies, project managers and consultants, as to how aesthetics can be incorporated into transportation projects. Study schedule to be determined. The approximate cost is $80,000. STATUS: Pending scope revision. Contact Susan Schreiber at 305-375-4507 for complete details.
  2. Citizen's Guide to Transportation 2004 (also known as Pocket Guide) - Created by FIU Metropolitan Center. “On the Move... Miami-Dade County’s Pocket Guide to Transportation” is the citizen's guide that provides transportation information to transit services, various highway services, bikes on trains and buses, greenways, ParaTransit and small mass transit services including vanpools, taxis, airport shuttles, carpooling, etc., and the ports. Download the Pocket Guide. Contact Elizabeth Rockwell at 305-375-4507 for complete details.
  3. Citizen's Guide to Transportation 2007 (also known as Pocket Guide) - Created by FIU Metropolitan Center. “On the Move... Miami-Dade County’s Pocket Guide to Transportation” is the citizen's guide that provides transportation information to transit services, various highway services, bikes on trains and buses, greenways, ParaTransit and small mass transit services including vanpools, taxis, airport shuttles, carpooling, etc., and the ports. Download the Pocket Guide, the Spanish Edition, and the Haitian Creole Edition. Contact Elizabeth Rockwell at 305-375-4507 for complete details.
  4. Community Characteristics Project Phase V 2008 - This involves the creation of a web-based application that enables transportation planners and public involvement offices (PIOs) to create an effective PI program and accomplish stated Title VI goals that will ultimately allow the identification of the attitudes and issues facing that particular community. Started January 2008 and completed January 2009. Work by Florida International University. The approximate cost was $60,000. RESULTS: Miami-Dade Transportation and Community Mapping website. Contact Elizabeth Rockwell at 305-375-4507 for complete details.
  5. Integrated Transportation Information System 2009 - ONGOING. Formerly known as Community Characteristics Project Phase VI. The objective is to review the social, economic, and geographic characteristics of an area before public involvement (PI) outreach is initiated. Started January 2009. Expected completion is March 2010. Work by Florida International University. The approximate cost is $63,000. Download the Scope of Services 2006-07. STATUS: 25% complete. A ITIS website is being developed to replace the Miami-Dade Transportation and Community Mapping website. Contact Elizabeth Rockwell at 305-375-4507 for complete details.
  6. Public Involvement Effectiveness Evaluation Program 2001 - The purpose of this study was to establish an evaluation program that can measure the effectiveness of the Miami-Dade MPO Public Involvement Program. The MPO Board approved and incorporated the program as part of the Miami-Dade Prospectus for Transportation. Innovative strategies were included as part of the plan that was fully endorsed by the Federal Highway Administration (FHWA). Work by Gannett Fleming. Download the Report. Contact Elizabeth Rockwell at 305-375-4507 for complete details.
  7. Sociocultural Effects Program 2003 - Formerly Community Impact Assessment Program. Studied from July 2003 to April 2005 (in two phases) by FIU Metropolitan Center; FIU GIS RS Center; and Urbana Research and Consulting, Inc. Connected to the Community Characteristics Project (CCP). The CCP is a tool which enables the Public Involvement Office (PIO) to review the social, economic, and geographic characteristics of an area before public involvement (PI) outreach is initiated. Phase I is a rudimentary web-based program utilizing ArcExplorer (shareware); while Phase II is program customized with added functionalities for a customer friendly environment. Contact Elizabeth Rockwell at 305-375-4507 for complete details.

Plans Studies: Involving master plans, mobility, intermodal and multimodal facilities. (next 31 study titles below)

  1. 79th Street Corridor Neighborhood Initiative 2002 - Also called 79th Street Corridor Redevelopment Plan or 79th Street Corridor Urban Study. To transform the portion of the 79th Street between NW 22nd Avenue and NW 42nd Avenue into a cohesive neighborhood. This includes a mixed-use transit oriented development, dedicated bus facilities, a kiss-and-ride facility, parking and the relocation of the Amtrak station, and a redevelopment of the Northside Shopping Center. The work was directed by the 79th Street Corridor Neighborhood Initiative, a partnership of non-profit economic development agencies. Started September 2002 and completed December 2003. Work by Zyscovich, Inc. Download the Final Report and Presentation. Contact Susan Schreiber at 305-375-4507 for complete details.

  2. City of Doral Transportation Master Plan 2005 - This report identified existing and future multi-modal transportation deficiencies and establish a program of transportation improvements in the City of Doral. Started March 2005 and completed May 2007. Work by the The Corradino Group. Download the Executive Summary and Final Report. Contact Oscar Camejo at 305-375-4507 for complete details.

  3. City of Doral Transportation Master Plan Update 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by the City of Doral. Budgeted cost is approximately $40,000. STATUS: Pending contract negotiation. Contact Oscar Camejo at 305-375-4507 for complete details.

  4. City of Homestead Downtown Area Transportation Plan Update 2003 - Updates the 1997 Homestead Traffic and Mobility Study, to resolve numerous transportation planning issues in Homestead's congested urban core. Specific measures to alleviate congestion have been recommended, but consensus has not been reached on methods of traffic calming, location for truck routes within the historic district, and bicycle lane placement vs. parking needs. Also, new transportation planning projects such as the Urban Transit Village and the new busway stop locations need to be incorporated in the existing plan. Started November 2003 and completed December 2005. Please visit our office to view or receive a copy of this report. Contact Larry Foutz at 305-375-4507 for complete details.

  5. City of Miami Beach Municipal Mobility Plan 1998 - The establishment of a transportation master plan for the City of Miami Beach. Completed December 1998. Work by The Corradino Group. Download the Executive Summary via MetroNet, or visit our office to view or receive a copy of this report. Contact Amelia Lopes-Johnson, City of Miami Beach, at 305.673.7550 for complete details.

  6. City of Miami Gardens Transportation Master Plan 2004 - This study will develop Miami Gardens' first transportation master plan as part of their Comprehensive Development Master Plan. Completed March 2006. Work by The Corradino Group. Download the Executive Summary and Full Report. Contact Larry Foutz at 305-375-4507 for complete details.

  7. City of North Miami Beach Community Mobility Program 2002 - A logical extension of the S.R. 826 Study and City Center Design Charrettes. It defines relationships between previous studies and provides a detailed work program for implementation. Work done by Chatterton Consulting. Download the Final Report, and Project Bank and Work Plan. Contact Jesus Guerra at 305-375-4507 for complete details.

  8. City of South Miami Hometown Intermodal Transportation Study 2002 - Reevaluate earlier transit-related studies concerning the City of South Miami central business district and immediate surrounding area (Hometown District) and develop a multimodal mobility plan. Completed in August 2002. Work by Kimley-Horn & Associates. Download the Executive Summary and Final Report. Contact Susan Schreiber at 305-375-4507 for complete details.

  9. Coastal Communities Transportation Master Plan 2006 - Produce short-, mid- and long-term multimodal solutions to transportation issues to the barrier island communities. Study the existing and future sub-regional transportation network through data collection, analysis and public involvement. Develop a multimodal list of projects and costs estimates. Prioritize projects into an implementable 10-year plan. Started February 2006 and completed June 2007. The final cost was $111,546. Download the Final Report, August 2007. Contact Wilson Fernandez at 305-375-4507 for more details.

  10. Coconut Grove Planning Study 1996 - For the development of a master plan for the Coconut Grove area which preserves the historical background of this community, reduce the negative impact of traffic flow, improve parking conditions and enhance the landscaping of the area. A review of land use policy and regulations is also included. Started April 1996 and completed October 1997. Work by Andres Duany and Elizabeth Plater-Zybeck, Architects, Inc.; Carr Smith and Associates; etc. Please visit our office to view or receive a copy of this report. Contact Larry Foutz at 305-375-4507 for complete details.

  11. Countywide Traffic Safety Program 2008 - ONGOING. A description of this study is forthcoming. Started January 2008. Expected completion was December 2008. Work by the University of Florida. The budgeted cost is approximately $100,000. Contact David Henderson at 305-375-1647 for complete details.

  12. Cutler Bay Transportation Master Plan 2008 - ONGOING. Study the existing and future conditions of the transportation system within the Town of Cutler Bay. Started September 2008. Expected completion was April 2009. The approximate cost is $100,000. Contact Wilson Fernandez at 305-375-4507 for complete details.

  13. Downtown Kendall Transportation Study 2002 - This study provides the Miami-Dade Planning & Zoning Department with documented information on the transportation related impacts associated with modifying roads in the Downtown Kendall Urban Center District. Work by Gannett Fleming. Please visit our office to view or receive a copy of this report. Contact Carlos Roa at 305-375-4507 for complete details.

  14. Feasibility Study: Northside Intermodal Terminal 1985 - It recommends the construction of an intermodal transportation facility with integrated parking structure at the Northside Metrorail Station. The proposed terminal would accommodate major Metrobus operations and a pedestrian overpass. Completed in 1986. Work by the Metro-Dade Transit Administration (now Miami-Dade Transit). Download the Report, February 1986. Contact Larry Foutz at 305-375-4507 for complete details.

  15. Golden Glades Multimodal Transportation Facility Feasibility Study 1994 - This study evaluates the feasibility of different conceptual designs for developing a multimodal facility at the Golden Glades Interchange, located in north central Miami-Dade County. Completed March 1994. Work by ICF Kaiser. Download the Executive Summary and Final Report. Contact Carlos Roa at 305-375-4507 for complete details.

  16. Health District Comprehensive Traffic Study 2008 - This study would document the traffic impacts of both the recent and forecast growth within the Health District/Civic Center Area. Performed between February 2008 and May 2009. Work by The Corradino Group. The approximate cost was $170,000. Download the Final Report. Contact Larry Foutz at 305-375-4507 for complete details.

  17. Improving Regional Transportation Planning 2009 - PENDING. This study would document the traffic impacts of both the recent and forecast growth within the Health District/Civic Center Area. The budgeted cost is approximately $25,000. STATUS: Pending contract with South Florida Regional Planning Council. Contact Susan Schreiber at 305-375-4507 for complete details.

  18. Kendall Drive Mobility Enhancement Study 2002 - This study was to develop improvement alternatives for potential FDOT and MDT work programs along Kendall Drive (SW 88th Street/SR94). Completed September 2002. Work by Gannett Fleming. Download the Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.

  19. Medley NW 116th Way Corridor Study 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by the Town of Medley. The budgeted cost is $31,335. STATUS: Pending contract negotiations. (October 2009) Contact Larry Foutz at 305-375-4507 for complete details.

  20. Miami Beach Intermodal Feasibility Study 1999 - Requested by the City of Miami Beach to perform an intermodal transit center feasibility study for it's electric shuttle (ElectroWave). Completed August 2000. Work by Corradino. Please visit our office to view or receive a copy of this report. Contact Susan Schreiber at 305-375-4507 for complete details.

  21. Miami Beach Master Plan for the 16th Street Corridor Study 2004 - ONGOING. A description of this study is forthcoming. Started September 2004. Expected completion during 2008. Contact Wilson Fernandez at 305-375-4507 for complete details.

  22. Miami Downtown Transportation Master Plan 2001 - Cooperatively funded by the City of Miami, the MPO, and FDOT. The DTMP will result in a guide for the City and its transportation planning partners in planning for the future downtown transportation system, and provide help in evaluating project proposals at operational levels, and to allow periodic updates to the transportation master plan as new development occurs. Completed April 2003. Work by David Plummer & Associates. Download the Executive Summary, Final Report, and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.

  23. Miami River Corridor Multimodal Transportation Plan 2006 - This plan identifies means to increase safety and mobility of freight, pedestrians, transit, and vehicular traffic in the historic Miami River corridor. Started April 2006 and completed August 2007. Work by Kimley-Horn & Associates. The approximate cost was $100,000. Download the Executive Summary, Final Report, and Appendices. Contact David Henderson at 305-375-1647 for complete details.

  24. Miami Springs Mobility Master Plan 2004 - A description of this study is forthcoming. Completed January 2004. STATUS: Awaiting final report. Contact Larry Foutz at 305-375-4507 for complete details.

  25. Palmetto Bay Transportation Master Plan Study 2004 - Palmetto Bay has adopted a master planning strategy to identify its existing and future transportation system deficiencies. It is expected that thousands of homes will be developed to the south of the city in the coming years. Started February 2004 and completed in 2004. Work by The Corradino Group (under contract with the Village of Palmetto Bay). Download the Executive Summary, Final Report, and its Appendix B: Stakeholders List (Traffic Data Collection & Analysis). Contact Larry Foutz at 305-375-4507 for complete details.

  26. Regional Long Range Transportation Plan 2007 - ONGOING. A description of this study is forthcoming. Started December 2007. Expected completion is March 2010. Work by Kittelson and Associates (via FDOT). The estimated cost to the MPO is approximately $150,000 (share of a tri-regional effort totaling $450,000). STATUS: 85% complete. Contact Wilson Fernandez at 305-375-4507 for complete details.

  27. Town of Miami Lakes Transportation Master Plan 2004 - This was to develop a plan for the Town of Miami Lakes to accommodate local mobility needs. Completed in February 2004. Work by Kimley-Horn & Associates. Download the Final Report. Contact Wilson Fernandez at 305-375-4507 for complete details.

  28. Transit Center Connections Study 2003 - Also called Connecting Traffic Generators Study 2003. This study identifies opportunities for improved intermodal connections and develop a tool for easy access to information regarding opportunities for such connections. The intermodal connections or “Transit Centers” are defined as transportation transfer points, providing access to transportation services, multiple services or modes. Studied from August 2003 to August 2004. Work by Cambridge Systematics. Download the Brochure and Final Report. Contact Carlos Roa at 305-375-4507 for complete details.

  29. Transportation Innovations in the 21st Century 2007 - ONGOING. This study will develop a menu of innovative cutting edge strategies for enhancing the county's transportation system in order to meet current and future transportation needs using strategies that employ state-of the art concepts in the areas of land use, safety, technology and environmental protection. The November 2007 completion not reached due to a scope revision, and remains ongoing. Started May 2007. Expected completion was November 2007. Work by the Center for Urban Transportation Research (CUTR). The expected cost is approximately $56,560. STATUS: 90% complete. Contact Jesus Guerra at 305-375-4507 for complete details.

  30. Transportation System Hurricane Emergency Preparedness Plan 1995 - A review of the transportation system during hurricane conditions. The results included a full inventory of the county's traffic signals and projected pre-storm evacuation roadway clearance times, among other things. Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Larry Foutz at 305-375-4507 for complete details.

  31. West Flagler Street Corridor Study 1997 - Seek solutions to mobility problems and promote transportation modes other than single-occupancy vehicles along West Flagler Street. Started in 1997 and completed September 1998. Work by Miami-Dade's Planning, Development and Regulation (now Miami-Dade Planning & Zoning Department). Download the Final Report and Implementation Measures. Contact Susan Schreiber at 305-375-4507 for complete details.

Roadways Studies: Looking at streets, roads, highways, and parking. (next 39 study titles below)

  1. 137th Avenue Corridor Study 2005 - Feasibility of making SW 137th Avenue into a major north/south corridor between the City of Homestead and central Miami-Dade County. Started in 2005 and completed June 2007. Work by The Corradino Group. Download the Executive Summary and Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  2. Access to SW 137th Avenue to and from SR 874 Study - Feasibility of creating a connection between SW 137th Avenue and State Road 874 also known as the Don Shula Expressway. Work by Kimley-Horn & Associates. Download the Executive Summary and Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  3. Adding Turbo Lanes to T-Intersections Study 2009 - ONGOING. Evaluate T-intersections that can be converted to turbo lanes within the county boundaries. Started May 2009. Expected completion is January 2010. Work by David Plummer & Associates. The budgeted cost is approximately $83,000 including 10% for contingencies. STATUS: 70% complete.  Contact Jesus Guerra at 305-375-1647 for complete details.
  4. Arterial Grid Network Analysis 2006 - intended to determine whether improvements could be made to the grid system as a long-term traffic congestion relief measure, rather than stop-gap improvements that may slightly improve traffic flow in one corridor while potentially “shifting” the problem to a different corridor. Started April 2006 and completed March 2007. Work by Kimley-Horn & Associates. Download the Executive Summary, Final Report, and Presentation. Contact Wilson Fernandez at 305-375-4507 for complete details.
  5. Arterial Investment Study: 107th Avenue - In conjunction with FDOT, a pilot Arterial Investment Study for SW/NW 107th Avenue was conducted to evaluate multimodal solutions. This study was considered as a pre-PD&E study, which resulted in a wide range of recommendations. Please visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.
  6. Bus-on-Shoulder Service Evaluation Study 2007 - This study will evaluate the operation of the “Bus on Shoulder” pilot project implemented along SR-874 (Don Shula Expressway) and SR-878 (Snapper Creek Expressway). Started September 2007 and completed January 2009. Expected completion was July 2008. Work by Parson Transportation Group. The approximate cost was $70,000. Download the Executive Summary and Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  7. City of North Miami Beach Fulford City Center Geometric Roadway Design Study 2003 - A look at creating a town center environment in an area called Fulford City Center within the City of North Miami Beach. Started April 2003 and completed May 2004. Work by Glatting Jackson Kercher Anglin Lopez Rinehart, Inc. Download the Final Report. Contact Larry Foutz at 305-375-4507 for complete details.
  8. Congestion Intersection Improvement Study Phase II 2006  - Evaluate congested intersections and recommend short-term traffic operational improvements for alleviating traffic congestion. Started August 2006 and completed March 2008. Work by David Plummer & Associates. The approximate cost was $97,900. Download the Executive Summary, Volume I, Volume II, and the Presentation. Contact Jesus Guerra at 305-375-4507 for complete details.
  9. Countywide High-Crash Location Safety Study 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by Miami-Dade Public Works. The budgeted cost is approximately $75,000. STATUS: Pending contract negotiation. (October 2009) Contact Wilson Fernandez at 305-375-4507 for complete details.
  10. Countywide Parking Policy Study for Miami-Dade County 1999 - This phase is a very comprehensive study which includes a set of recommended parking policies and strategies by area of action, from coordination to enforcement. Completed in August 1999. Work by Barton-Aschman Associates, Inc; Parsons Transportation Group. Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.
  11. Curtiss Parkway/NW 36 Street Traffic Study 2005 - A study to assess the impact on traffic flow at the intersection of Curtiss Parkway and NW 36th Street that would be caused by the City of Miami Springs' proposed redevelopment of that area. Started December 2005 and completed May 2006. Work by David Plummer & Associates. Download the Final Report. Contact Larry Foutz at 305-375-4507 for complete details.
  12. Flagler Street Reversible Flow Study 1992 - This study would provide a more in-depth analysis of the pros and cons of providing reversible traffic flow on certain lanes of West Flagler Street between 27th Avenue and the Palmetto Expressway. Completed in May 1992. Work by Transport Analysis Professionals, Inc. Download the Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  13. I-395 Alternatives Financial Assessment Study 2002 - The objectives were to review the three alternatives to replace the existing I-395 structure, develop two new potential alternatives that can more effectively meet the objectives of the stakeholders involved, and perform a financial analysis to determine the financing necessary to implement the recommended solution. The basic goal of this study is to reach a consensus among FDOT, the MPO, and the City of Miami as to a viable alternative, which will allow FDOT’s I-395 Project Development & Environment (PD&E) study to recommence. Started in 2002 and completed April 2004. Work by Kimley-Horn & Associates. Download the Final Report and the Pre-study Review. Contact Jesus Guerra at 305-375-4507 for complete details.
  14. Indirect Left Turns Study 2007 - This study will address the potential of increasing efficiency and capacity at major intersections in Miami-Dade County through the elimination of left turns and replacing them with right turn loops. Started in November 2007 and completed December 2008. Expected completion was July 2008. Work by David Plummer & Associates. The approximate cost was $50,000. Download the Executive Summary, Final Report, and Presentation. Contact Wilson Fernandez at 305-375-4507 for complete details.
  15. Metro-Dade Road Pricing Study 1994 - This studied if the county's congestion could be mitigated through creative pricing solutions that would provide motorists, particularly single occupant vehicles (or SOV), with financial incentives sufficient to alter their travel behavior. Started in 1994 and completed early-1995. Work by Kimley-Horn & Associates, Barbara Howard & Associates, and Kittelson & Associates. Download the Final Report. Contact MPO Staff at 305-375-4507 for complete details.
  16. Metropolitan Planning Organization Congested Intersections Study 1999 - This study was developed to support the Resourceful Use of Streets and Highways (RUSH) Program recommended in the Miami-Dade Congestion Management System (CMS). A criteria was developed to evaluate over 150 intersections. Traffic improvements were recommended for 20 locations. Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.
  17. Miami Springs 36th Street District Traffic Impact Study 2010 - PENDING. Analyze impacts on traffic in Miami Springs along NW 36th Street. Study schedule to be determined. The budgeted cost is approximately $20,000. STATUS: Pending consultant negotiation. Contact Wilson Fernandez at 305-375-4507 for complete details.
  18. Miami-Dade County Grade Separation Feasibility Study 2004 - This study was created to assess if the concept of grade separations and urban interchanges is viable or fatally flawed for implementation on major city streets along serving the main county travel corridors. These types of roadway lanes will allow traffic to bypass sign and/or signal-controlled intersections. The result is reduced congestion by way of continual traffic flow through an intersection akin to expressway interchanges. Completed May 2005. Work by Corradino. Download the Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  19. Miami-Dade County Typical Roadway Section and Zoned Right-of-Way Update Study 2007 - To update typical streets section standards through the County with special emphasis on the urban centers and review countywide zoned right-of-ways widths, and recommend revised zoned R-O-W for roadways in the county. Completed December 2007. Work by Kimley-Horn & Associates. The approximate cost was $110,000. Download the Workbook. RESULTS: Draft zoned R-O-W ordinance to be sent to BCC via Department of Planning and Zoning. Contact Jesus Guerra at 305-375-4507 for complete details.
  20. Miracle Mile Traffic Circulator Study 1993 - This study described the methods that were used to develop traffic and parking improvements plan that would return Miracle Mile (City of Coral Gables) to a more pedestrian oriented, shopping friendly environment. Completed in May 1994. Work by David Plummer & Associates. Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Irma San Roman at 305-375-4507 for complete details.
  21. NE Corridor Traffic Flow Implementation Plan Study 2008 - ONGOING. This study will implement the improvements specified by the Northeast Miami-Dade Traffic Flow Study 2006. Started in December 2008. Expected completion was September 2009. Work by Kimley-Horn & Associates. The approximate cost is $75,000. STATUS: 85% complete. Contact Larry Foutz at 305-375-4507 for complete details.
  22. North Miami Beach US-1/NE 163rd Street Intersection Study 2007 - ONGOING. A description of this study is forthcoming. Started December 2007. Expected completed was September 2008. Work in conjunction with the City of North Miami Beach. The cost is part of the Municipal Grant Program. Contact Oscar Camejo at 305-375-4507 for complete details.
  23. North Ponce de Leon Boulevard Median Evaluation 2002 - Development of a raised median on Ponce de Leon Blvd. between Alcazar Avenue and 8th Street in Coral Gables. It will review the capacities and service levels of the existing street cross sections, crash-prone locations and pedestrian movements. And evaluate the City of Coral Gables' transit circulator. Work by David Plummer & Associates. Download the Executive Summary and Final Report. Contact Irma San Roman at 305-375-4507 for complete details.
  24. Northeast Miami-Dade Traffic Flow Study 2006 - Improve traffic flow along the Miami-Dade northeast corridor. It will define improvements that would accommodate future growth, protect and enhance mobility and economic prosperity and quality of life within the study area. It will also help municipalities identify areas of congestion and provide options to relieve for the same. Started July 2006 and completed September 2007. Work by the City of North Miami Beach. The approximate cost was $67,200. Download the Executive Summary, Task 1 and 2 reports, Task 3 report, Task 4 and 5 reports, and Appendix A and B. Contact Larry Foutz at 305-375-4507 for complete details.
  25. NW/NE 36th Street Study 2006 - Evaluate traffic flow conditions along 36th Street and adjacent areas. Started August 2006 and completed June 2007. Work by Kimley-Horn & Associates. The approximate cost was $80,000. Download the Executive Summary and Final Report. Contact Larry Foutz at 305-375-4507 for complete details.
  26. NW 7th Avenue Traffic and Pedestrians Study 2009 - ONGOING. A description of this study is forthcoming. Started May 2009. Expected completion is January 2010. Work by The Corradino Group. The budgeted cost is approximately $90,000. STATUS: 75% complete. Contact Larry Foutz at 305-375-4507 for complete details.
  27. Post Hurricane Short Range Transportation Study 1995 - It was created to define the existing transportation conditions in the West Miami-Dade Area. Recommendations were made to maintain acceptable levels of service on roadways that improve mobility options in the area. Improvements include short and long term projects. Please visit our office to view or receive a copy of this report. Contact Carlos Roa at 305-375-4507 for complete details.
  28. South Dade Managed Lanes 2007 - The objective of this study is to identify reasonable alternatives for developing of managed lanes in the right-of-way of the South Dade Busway and to evaluate the revenue generating potential. Started July 2007 and completed September 2008. Expected completion was June 2008. Work by Kimley-Horn & Associates. The approximate cost was $80,000. Download the Executive Summary, Final Report, and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.
  29. Special Use Lane Study 2004 - Also called Reversible Lanes. This study makes a quick examination of freeway facilities and major arterials that have the potential to accommodate special use lanes, which could be reversible or could be used by regular traffic, high-occupancy vehicles (HOV), bus rapid transit, or some mixture of the three. Completed in 2004. Work by The Corradino Group and PMG Associates, Inc. Download the Brochure and Executive Summary. Contact Jesus Guerra at 305-375-4507 for complete details.
  30. Special Use Lanes Study: Transit Use of Shoulder By-Pass Lanes 2005 - This study evaluates the condition of the shoulders along the expressway system for allowing transit buses to use it as a by-pass lane for traffic congestion. Segments were identified, as appropriate and an action plan was developed. A pilot project will be implemented in phases. Completed in November 2005. Work by The Corradino Group. Download the Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  31. Superarterial Network Study 1996 - This study identifies corridors and improvements for developing a superarterial network to alleviate existing traffic congestion along the expressway system. Completed October 1998. Work by Parsons, Brinckerhoff, Quade & Douglas, Inc. Download the Final Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Larry Foutz at 305-375-4507 for complete details.
  32. SW 152nd Street Corridor Transportation Study 2007 - Identify alternatives for improving traffic flow along SW 152nd Street, from US-1 to 162nd Avenue. Started March 2007 and completed July 2008. Work by Gannett Fleming. The approximate cost was $80,000. Download the Executive Summary Report and Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.
  33. Town of Medley NW South River Drive Corridor Study 2003 - Also called South River Drive Corridor. This study was to provide the Town of Medley and the Miami-Dade MPO with information on the existing conditions along NW South River Drive, between NW 107th Avenue and the Palmetto Expressway, and the need for improvements. Completed December 2003. Work by Corzo Castella Carballo Thompson Salman, P.A. Download the Volume 1 Engineering Analysis. Contact Jesus Guerra at 305-375-4507 for complete details.
  34. Town of Medley NW South River Drive Corridor Area Expansion Study 2005 - Also called Medley, Phase II or South River Drive Corridor II. This was created to investigate transportation characteristics and deficiencies associated with the Town of Medley's westernmost industrial area and its interaction with SR-25. Completed November 2005. Work by Corzo Castella Carballo Thompson Salman, P.A. Download the Volume 1 Master Plan, Volume 1 Appendix, Volume 2 Master Plan and Volume 2 Appendix. Contact Jesus Guerra at 305-375-4507 for complete details.
  35. Traffic Signs Research Study for Miami-Dade County 2006 - Evaluate a set of feasible alternatives for improving withstanding capabilities, in the event of a hurricane, of the street signs without making the installation process more difficult. Completed in 2007. Work by the Center for Urban Transportation Research and the University of South Florida. Download the Executive Summary, Final Report, or Presentation. Contact Jesus Guerra at 305-375-4507 for complete details.
  36. US-1 Intersection Improvements Study 2007 - This study investigates the operational and safety needs and improvement alternatives for 12 intersections along US 1, between SW 72nd Avenue and SW 136th Street, on the eastern boundary of the Village of Pinecrest. Completion is tentative on study presentation to committee. Started September 2007 and completed April 2008. Work by the Village of Pinecrest and Florida International University. The approximate cost was $30,000. Download the Report and Presentation. Contact Oscar Camejo at 305-375-4507 for complete details.
  37. US-1 Reversible Flow Lane Study 2006 - Study the feasibility of developing a master plan for the addition of two reversible lanes along US 1 between I-95 and Bird Road. Started August 2006 and completed December 2007. Work by The Corradino Group. The approximate cost was $55,000. Download the Executive Summary, Final Report and Presentation. Contact Larry Foutz at 305-375-4507 for complete details.
  38. US-1/SR-878 Intersection Sub-Area Traffic Study 2009 - ONGOING. A description of this study is forthcoming. Started May 2009. Expected completion is November 2009. Work by David Plummer & Associates. The budgeted cost is approximately $62,000. STATUS: 70% complete. Contact Wilson Fernandez at 305-375-4507 for complete details.
  39. Westchester Traffic Impact Study 2007 - The study will evaluate current and future traffic conditions as a result of new development and roadway improvements in the Westchester area. The area is defined as: Palmetto Expressway to the east, Krome Avenue to the west, S.R. 836 to the north, and Miller Drive/SW 56th Street to the south. Started April 2007 and completed June 2008. Work by Gannett Fleming. The final cost was $54,986. Download the Final Report of June 30, 2008. Contact Wilson Fernandez at 305-375-4507 for complete details.

Systems Studies: Dealing with congestion management, ITS, and technology related solutions. (next 19 study titles below)

  1. Congestion Management Process (CMP) Update 2009 - ONGOING. This study will update the Congestion Management System (CMS) to reflect the new Federal requirement established under SAFETEA-LU. This update will be incorporated in the 2035 LRTP, as a planning tool, as recommended in the 2007 Miami-Dade MPO Federal Certification. It was expected to end during May 2009, but is still ongoing. Started in September 2008. Work by Gannett Fleming. The approximate cost is $79,439. STATUS: 90% complete. Contact Jesus Guerra at 305-375-4507 for complete details.

  2. Congestion Management System Update Study 2003 - This updates the CMS/MMP. It also establishes a Study Advisory Committee and web-based nationwide research regarding activities conducted in other cities to alleviate traffic congestion. Based on these findings, Kimley-Horn developed criteria to determine the congested corridors within the county, and identified strategies to improve mobility there. Started October 2003 and completed November 2004. Work by Kimley-Horn & Associates. Download the Final Report, November 2004. Contact Jesus Guerra at 305-375-4507 for complete details.

  3. Feasibility of Implementing Tech Centers in Miami-Dade County 2004 - The objective was to assess the feasibility of implementing technology centers to alleviate traffic congestion as an alternative means of maximizing the efficient use and capacity of limited transportation recourses. Completed in July 2006. Work by the Center for Urban Transportation Research (CUTR). Download the Executive Summary and Final Report of July 13, 2006. Contact Jesus Guerra at 305-375-4507 for complete details.

  4. Fiber Optic Communications Concept Plan for Miami-Dade County's Intelligent Transportation Infrastructure 1998 - Defining a conceptual plan for establishing a fiber optic communications network capable to support Miami-Dade County's intelligent transportation system infrastructure. Completed in 1998. Work by Center for Urban Transportation Research (CUTR). Download the Final Report, June 1998. Contact Carlos Roa at 305-375-4507 for complete details.

  5. Integrated Transportation Management System (ITMS) 1998 - The ITMS is based on a GIS platform which incorporates different data sources to generate reports, tables, maps and graphics, as an excellent working tool in the decision-making process. The ITMS includes the following management systems: Congestion (CMS), Pavement (PMS), Intermodal (IMS), Public Transportation (PTMS), Safety (SMS) and the Traffic Monitoring System for Highways (TMS/H). Work by David Plummer & Associates. Download the Final Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.

  6. Intelligent Transportation System Plan for Dade County 1996 - Created to establish a general policy planning process for ITS projects, and coordinate and integrate all efforts conducted by different entities in the same area. Completed July 1996. Work by the MPO staff. Download the Report. Contact Carlos Roa at 305-375-4507 for complete details.

  7. Intelligent Transportation System (ITS) Plan Update for Miami-Dade County 1999 - Indentifies ITS enabling projects that are most critical in deployment of a regional ITS system, as well as other ITS "enhancements" to traditional transportation improvement projects and services that are location specific. Work by the Center for Urban Transportation Research. Download the Final Report. Contact Carlos Roa at 305-375-4507 for complete details.

  8. InteracTIP 2003 - This endeavor automated the annual development of the TIP. Emphasis was made on improving consistency; making the TIP book more user-friendly; creating special reports to answer questions from the general public; facilitating the analysis of the data; and providing easy access to information by the public on the internet via Miami-Dade's My Neighborhood website. Completed in January 2004. Work by David Plummer & Associates and International Development Analysis Services (IDAS). Download the Executive Summary, Final Report, and Presentation. Updates: 2007 update - Completed in July 2007. Resulted in the InteracTIP 2008 website (defunct). 2008 update - Developed from January 2008 to November 2008. The approximate cost was $54,700. Resulted in the InteracTIP 2009 website (defunct), and InteracTIP MAPS website. 2009 update - ONGOING. Started March 2009. Expected completion January 2010. The approximately cost is $55,000. STATUS: 90% complete. STATUS: InteracTIP 2010 website. Contact Carlos Roa at 305-375-4507 for complete details.

  9. InteracTIP Project Tracking System 2010 - PENDING. The proposed system would supplement the on-line capabilities of the InteracTIP to allow users to see the status of projects that are in previous TIPs. The application would be integrated with the existing InteracTIP process. It would be capable of: 1) identifying capacity related construction projects over $500,000 that appeared programmed on the first year of the FY 2005 TIP and have yet to begin deployment phases; 2) identifying a maximum of 30 projects to be included in this process that are still pending for completion; 3) monitoring the status of the selected projects on a quarterly basis or as determined by the MPO project manager; and, 4) providing a tool for listing the reasons for projects delay. Study schedule to be determined. The budgeted cost is approximately $58,000. STATUS: General Planning Consultant (GPC) to be selected. (October 2009) Contact Carlos Roa at 305-375-4507 for complete details.

  10. Interactive Transportation Information Systems (Kiosk) 1997 - To provide better information to travelers in the trip decision making process, in order to increase overall mobility in the area. Completed in December 1997. Work by Center for Urban Transportation Research (CUTR). Please visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.

  11. LeJeune Road Corridor Traffic Impact Study 1996 - A study to identify and evaluate potential low-cost improvements for the area defined by LeJeune Road, South Royal Poinciana Boulevard, and NW 36th Street. Completed July 1996. Work by Kimley-Horn & Associates. Download the Draft Final Report, July 1996. Contact Oscar Camejo at 305-375-4507 for complete details.

  12. Mobility Management Process/Congestion Management System 1996 - In compliance with ISTEA, Miami-Dade County developed a MMP/CMS for defining congested corridors and identifying strategies for alleviating traffic congestion. Work by David Plummer & Associates. Please visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.

  13. Model Validation to Cube Voyager 2007. To review and validate the Miami-Dade County model, currently under FSUTMS and supported with TRANSPLAN, to the new software engine of FSUTMS called Cube Voyager. Started December 2007 and completed September 2008. Expected completion was January 2008. Work by The Corradino Group. The approximate cost was $55,000. Download the User's Guide, September 2008. Contact Larry Foutz at 305-375-4507 for complete details.

  14. Opa-Locka Sound Barrier Alternatives Study 2008 - PENDING. This study will evaluate sound barrier alternatives for alleviating noise conditions along the South Florida rail corridor within the City of Opa-Locka. Study schedule to be determined. Budgeted cost is approximately $65,000. STATUS: Pending funds from FDOT. Contact Jesus Guerra at 305-375-4507 for complete details.

  15. Simulation and Analysis of Potential Mass Evacuation of Miami-Dade Residents 2006 - Requested by CTAC in response to the mass evacuation that followed Hurricane Katrina's impact on New Orleans and Hurricane Rita's impact on Houston. Completed June 2007. Work by Gannett Fleming and Advanced Transportation Engineering Consultants. Download the Final Report, June 2007. Contact Oscar Camejo at 305-375-4507 for complete details.

  16. South Florida Clean Energy and Greenhouse Gas Emission Reduction Program 2009 - ONGOING. It will accelerate the growth and development of alternative fuel fleets, fuel suppliers and awareness in the four county regions. Started April 2009. Expected completion is March 2010. Work by the South Florida Regional Planning Council (SFRPC). The approximate cost is $50,000. STATUS: 80% complete. Contact Susan Schreiber at 305-375-4507 for complete details.

  17. Transportation Data Management System (TDMS) 2001 - Implement a flexible, expandable, computer-based electronic MPO-resident relational database to hold and husband transportation and transportation-related data that will allow statistical, temporal, and geographic analyses, and be capable of report, tabular, graph, and map presentation of information. Completed March 2002. Work by David Plummer & Associates, and International Development Analysis Services. Download the Executive Summary and Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.

  18. Transportation System Performance Monitoring 2007 - This study would identify a series of performance measures that can be collected on an annual basis to have a method of tracking changes in the quality and level of service on the transportation system. Started September 2007 and completed February 2009. Expected completion was August 2008. Work by Gannett Fleming. The approximate cost was $59,912. Download the Report and State of the County. Contact Larry Foutz at 305-375-4507 for complete details.

  19. Update of the Miami-Dade County GIS Crash Data System 2009 - PENDING. To update the crash data system with the 2009 Florida Department of Highway Safety and Motor Vehicles crash data. Miami-Dade County receives data and scanned images of crash reports on monthly basis. The University of Florida (UF) team will obtain, cleanse, standardize, map and upload the 2009 crash data into the Miami-Dade crash data system. All crash data, including bicycle and pedestrian, will be processed. In addition, the UF team will train county personnel in the aforementioned processes as well as update the crash data system with any new features that may be available as system is improved. Study schedule to be determined. Work by Miami-Dade Public Works and University of Florida. The budgeted cost is approximately $50,000. STATUS: Pending contract negotiation. (October 2009) Contact Carlos Roa at 305-375-4507 for complete details.

Transit Studies: Related to buses, trains, carpools, trolleys, ride-sharing, and mass transport. (next 41 study titles below)

  1. Bay Link (Miami-Miami Beach Transportation Corridor Study 2002) - This would study a double tracked, street-level light rail alignment that would serve downtown Miami, Watson Island, and the southern portion of Miami Beach. Two rounds of public meetings (each) were held separately in Miami and Miami Beach. One to outline the system and the other to get comments and concerns. Completed August 2004. Work by Parsons Brinckerhoff. Download the Presentation to the MPO on July 29, 2004. RESULTS: Systems planning was completed October 2002. Alternatives Analysis/Draft Environmental Impact Statement was done May 2003. A Locally Preferred Alternative (LPA) was adopted by the MPO on September 26, 2003. And PE/Final Environmental Impact Statement was completed August 2004. Contact Wilson Fernandez at 305-375-4507 for complete details.

  2. Bus Rapid Transit Opportunities Study 2003 - This project will explore the potential for implementing relatively low-cost BRT service in the major and secondary corridors and arterial streets that are anticipated to have substantial bus service in place, and to identify the most feasible types of BRT improvements that can be made. Started October 2003 and completed March 2005. Work by the Center for Urban Transportation Research (CUTR). Download the Technical Memorandum No. 1, Technical Memorandum No. 2, and Technical Memorandum No. 3. Contact Wilson Fernandez at 305-375-4507 for complete details.

  3. City of Aventura Municipal Transit Study 1998 - The objective was to implement a municipal public transit system to serve it's 3.2 square mile area which was previously serviced by Miami-Dade Transit, Broward County Transit, and private shuttle systems. The study would recommend a system with universal access to all residents of the City of Aventura. Completed in 1998. Work by Bermello Ajamil & Partners, Inc. Download the City of Aventura Municipal Transit Study Final Report, June 1998. Contact Oscar Camejo at 305-375-4507 for complete details.

  4. City of Coral Gables Circulator System Study 1996 - Investigate the feasibility of a transit circulator along Ponce de Leon Boulevard corridor which would provide connectivity to the Downtown/Miracle Mile area, SW 8th Street, and the Metrorail. Completed in 2001. Work by David Plummer & Associates. Download the City of Coral Gables Circulator System Study Report, May 2001. Contact Larry Foutz at 305-375-4507 for complete details.

  5. City of Hialeah Circulator Study 1997 - he objective of this study was to explore the feasibility of implementing a local bus service for the City of Hialeah. The service would be coordinated with other public transportation providers in the area. Additionally, the study included available funding sources to implement the service. Download the City of Hialeah Circulator Study Final Report, October 1998. Contact Larry Foutz at 305-375-4507 for complete details.

  6. City of Miami Feasibility Study to Implement Car-Sharing Programs 2009 - PENDING. Conduct a feasibility study to implement car-sharing program in the City of Miami. Study schedule is to be determined. Work may be performed by the City of Miami or a consultant or through the Miami-Dade County's Equitable Distribution Program (EDP). The approximate cost is $25,000. STATUS: Funding not available. Conductor of study to be determined. (November 2009) Contact Jesus Guerra at 305-375-4507 for complete details.

  7. City of South Miami Trolley/Circulator Feasibility Study 2006 - Develop a plan for the establishment of a pilot service program that would integrate the City of South Miami's trolley service with other area shuttle and trolley services. Started August 2006 and completed August 2007. Work by Parsons Transportation Group. The approximate cost was $75,000. Download the Executive Report. Contact Larry Foutz at 305-375-4507 for complete details.

  8. Coral Gables Trolley Route Expansion Study 2005 - Assess the feasibility of routes that connect the Coral Gables Trolley to the Flagler Street corridor, the MacFarlane Homestead Historic District, the University of Miami, and the Riviera Business District. And identify preliminary trolley stops/spacing. Completed in early 2006. Work by David Plummer & Associates. Download the Executive Summary, Feasibility Report, and Presentation. Contact Irma San Roman at 305-375-4507 for complete details.

  9. Countywide Park and Ride Facilities Study 2009 - PENDING. A description of this study is forthcoming. Study schedule is to be determined. The budgeted cost is approximately $35,000. STATUS: Equitable Distribution Program (EDP) firm to be selected. (October 2009) Contact Wilson Fernandez at 305-375-4507 for complete details.

  10. Doral Circulator Study 2006 - Examined potential circulator transit in the City of Doral by examining the existing service, the population demographics of income and transit dependency, as well as potential user groups. Started July 2006 and completed June 2007. Work by The Corradino Group. The approximate cost was $34,800. Download the Doral Circulator Study Final Report, May 2007. Contact Larry Foutz at 305-375-4507 for complete details.

  11. East West Corridor Study - The East-West Corridor is a multimodal solution for severe traffic congestion along SR 836, the only east-west expressway in central Miami-Dade County. The project combines highway and transit improvements, running along SR 836 and connecting the Florida International University, the Miami Intermodal Center (MIC), downtown Miami and the Port of Miami. The estimated cost is $1.7 billion. Download the Airport Area Multimodal Access Study 1992 Executive Summary. RESULTS: Construction began January 2003 on the MIC or Orange Line Phase 1 by Earth Tech. Tentative completion is May 2011. Preliminary engineering for the Orange Line Phase 3 has begun. Contact Wilson Fernandez at 305-375-4507 for complete details.

  12. Electric Transit Circulator Feasibility Study 2000 - Explored possibilities and problems of implementing local transit circulators that would run on electric or hybrid-electric vehicles. Started in 2000. Work by the Center for Urban Transportation Research (CUTR). Completed June 2001. Download the Final Report and Presentation. Contact Jesus Guerra at 305-375-4507 for complete details.

  13. Electrowave Shuttle Report 1998 - This study summarized the activities and results of the ELECTROWAVE shuttle service implemented in the Miami Beach area during 1998. Please visit our office to view or receive a copy of this report. Contact Judy Evans, Miami Beach TMA Executive Director, at 305.535.9160 for complete details.

  14. Evaluation of Miami-Dade Transit's Trunk and Feeder Bus System Study 2009 - PENDING. The objective of this study is to evaluate the Trunk and Feeder Bus System to be implemented by Miami-Dade Transit (MDT). Study schedule to be determined. The budgeted cost is approximately $85,000. STATUS: On-hold until February 2010, awaiting route changes by MDT. (November 2009)Contact Jesus Guerra at 305-375-4507 for complete details.

  15. Feasibility Study: A Public-Private Partnership for Transit Vehicle Purchasing and Leasing 1998 - Determine the feasibility of using Miami-Dade Expressway Authority (MDX) funds to serve as the local match for federal grants to purchase small transit vehicles. These vehicles would then be leased to private or public sector operators to provide additional public transit services that would complement existing transit services. Started in 1998. Download the Report. Contact Larry Foutz at 305-375-4507 for complete details.

  16. Florida East Coast (FEC) Transit Connection Study 2009 - ONGOING. This study will provide a status report on recent developments and evaluate the feasibility of implementing transit services along FEC corridor from MIA to the Dadeland area to complement a planned bicycle trail facility also known as the Ludlam Trail project. Started July 2008. Work by Kimley-Horn & Associates. Expected completion was April 2009. The approximate cost is $70,000. STATUS: 85% complete. Contact Wilson Fernandez at 305-375-4507 for complete details.

  17. Hialeah Transit System Express Service Feasibility Study 2009 - PENDING. A description of this study is forthcoming. Study schedule to be determined. Work by the City of Hialeah. STATUS: Pending contract negotiation. (October 2009) Contact Wilson Fernandez at 305-375-4507 for complete details.

  18. Hialeah Transit System Services And Opportunities Study 2003 - This study looked into improving the Hialeah Transit Service (HTS) and evaluating performance of the newly implemented system and recommending any adjustments. Work by The Corradino Group. Completed December 2003. Download the Final Report. Contact Wilson Fernandez at 305-375-4507 for complete details.

  19. Investigation of Alternative TMAs 1994 - This study was conducted to investigate alternative Transportation Management Associations (TMA) whose programs were not solely employer-based. Started in 1994. Work by Barton-Aschman & Associates. Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.

  20. Kendall-Link Alternatives Analysis Study 2005 - The study was a re-evaluation alternative analysis for rapid transit improvements in the Kendall Corridor area (along Kendall Drive/SW 88th Street from the Dadeland area to SW 157th Avenue) connecting both to existing and future Metrorail facilities in the Dadeland and FIU areas. The study will lead to the selection of a locally preferred alternative which will consist of rapid transit improvements. Started November 2005 and completed September 2007. Work by Edwards & Kelcey. The approximate cost was $837,000. Download the Click here to see list of documents. Contact Wilson Fernandez at 305-375-4507 for complete details.

  21. Local Municipal Transit Circulator Policy Study 2002 - The objectives of this study are: 1) to develop a set of guidelines and standards for implementing transit circulators; and 2) to develop performance measures for evaluating implemented transit circulators. Completed in June 2002. Work by Kimley-Horn & Associates. Download the Executive Summary and Final Report. Contact Wilson Fernandez at 305-375-4507 for complete details.

  22. Locate Sites for Bus Shelter Installations 2009 - ONGOING. Identify sites suitable for the immediate installation of bus shelters. Started November 2008. Expected completion was July 2009. Work by David Plummer & Associates. The approximate cost was $56,448. STATUS: 95% complete. Contact Larry Foutz at 305-375-4507 for complete details.

  23. Metrorail/Coconut Grove Connection Study Phase II 2004 - This study examines the feasibility of implementing an exclusive right-of-way transit connection between the Metrorail line and the Coconut Grove Village Center. It looks at possible transit modes, local systems implemented or planned, national and international research, and a comparative analysis of transit alternatives for the project. Completed in January 2007. Work by Reynolds, Smith & Hills, Inc. Please visit our office to view or receive a copy of this report. Contact Wilson Fernandez at 305-375-4507 for complete details.

  24. Miami Civic Center Circulator Study 2005 - As part of an economic development plan developed for the City of Miami, this study would determine the feasibility of a circulator system to serve the Civic Center area. Started in 2005 and completed February 2006. Work by The Corradino Group. Download the Miami Civic Center Circulator Study Final Report, February 2006. Contact Larry Foutz at 305-375-4507 for complete details.

  25. Miami Civic Center Circulator Study Phase II 2007 - ONGOING. As a continuation of Phase I, it will focus in more detail on implementation, routes and cost estimates, contractual management and operation options analysis, and financing plan. Started in April 2007. Expected completion was December 2008. Work by The Corradino Group and the City of Miami's Office of Grant Administration. The approximate cost is $48,000. Part of the Municipal Grant Program. Contact Larry Foutz at 305-375-4507 for complete details.

  26. Miami Gardens Circulator Feasibility Study 2006 - Develop a plan for the establishment of a transit circulator service, in the City of Miami Gardens, that would integrate with other transit services in the community. Started August 2006 and completed February 2008. Work by David Plummer & Associates. The approximate cost was $50,000. Download the Executive Summary, Final Report, and Presentation. Contact Carlos Roa at 305-375-4507 for complete details.

  27. Miami Springs Transit System Service and Opportunity Study 2004 - This study was part of the Municipal Grant Program (MGP) to provide a factual basis for decision-makers seeking to improve the quality of life in the City of Miami Springs via improved local transit. Completed November 2004. Work by The Corradino Group. Download the Final Report, November 2004. Contact Jesus Guerra at 305-375-4507 for complete details.

  28. Miami Surface Shuttle Services Technical Assistance 2000 - Evaluate the feasibility of implementing shuttle services for the airport west and downtown Miami areas. Completed June 2000. Work by Center for Urban Transportation Research (CUTR). Download the Report via MetroNet, or visit our office to view or receive a copy of this report. Contact MPO Staff at 305-375-4507 for complete details.

  29. North Miami Community Transit Circulator Study 2000 - An analysis of the need and feasibility of public community transit services using minibuses, integrated with existing public and private transit services, to serve the City of North Miami and neighboring areas. The provision of coordinated community-level transit service supports the major recommendation of the Miami-Dade Transit’s 1995 Northeast Dade Transit Improvement Study. Completed in April 2000. Work by PRL & Associates, and North Meridian, Inc. Download the Executive Summary and Final Report, April 26, 2000. Contact Oscar Camejo at 305-375-4507 for complete details.

  30. Opa-Locka Circulator/Transit Improvement Feasibility Study 2008 - ONGOING. Develop a transit system within the limits of the City of Opa-Locka. Alternatives should be developed considering different modes. Started in December 2008. Expected completion was July 2009. Work by the City of Opa-Locka. The approximate cost is $70,000. STATUS: 50% complete. Contact Wilson Fernandez at 305-375-4507 for complete details.

  31. Palmetto Corridor Light Rail Transit Feasibility Study 1996 - Evaluating the feasibility of implementing a light rail transit project along the Palmetto Expressway (SR 826). Two alternatives were considered: A) Dadeland North Metrorail Station to SR 836 and then to the proposed MIC and; B) Dadeland North Metrorail Station to Okeechobee Metrorail Station along the Palmetto Expressway. Alternative "A" was included for consideration in the LRTP. Completed in 1997. Work by Gannett Fleming. Download the Final Report, January 1997. Contact Carlos Roa at 305-375-4507 for complete details.

  32. Service Enhancements to the Hialeah Transit System 2007 - ONGOING. This study examines potential HTS express transit service by examining the existing service with the intention of providing services on less congested roads on the periphery of the city and linking key attractions and destinations. Started January 2007. Work by the City of Hialeah. The approximate cost is $20,000, part of the Municipal Grant Program. Contact David Henderson at 305-375-1647 for complete details.

  33. Snapper Creek Park & Ride Feasibility Study 1999 - To assess the feasibility of implementing a park and ride facility at the Snapper Creek Service Plaza on Florida's Turnpike. The feasibility considerations include the demand for the facility, and accessibility and operational impacts on the Turnpike and the Service Plaza. Started in 1999. Download the Final Report via MetroNet, or visit our office to view or receive a copy of this report. Contact Rafael De Arazoza, of FDOT, at 850.414.4100 for complete details.

  34. South Link (South Miami-Dade Transit Corridor Study 2004) - An alternative analysis to develop transportation improvements for the corridor that stretches from the Dadeland South Metrorail Station to Florida City. The focus was on those projects already funded and under construction, in order to keep pace with the rapid population growth and forecasted travel needs for the South Miami-Dade area. Completed January 2006. Work by The Corradino Group. Download the Click here to see list of documents. Contact Wilson Fernandez at 305-375-4507 for complete details.

  35. Town of Medley Transit Circulator Services Implementation Study 2005 - It provided the Town of Medley and the MPO with a comprehensive evaluation of existing public transportation system deficiencies; determine existing and potential transit needs; recommend a transit circulator system and strategy; and, a preliminary cost estimate and potential funding sources. Started August 2005 and completed September 2006. Work by BCC Engineering and Westhorp & Associates. Download the Executive Summary and Full Report. Contact Jesus Guerra at 305-375-4507 for complete details.

  36. Transit Contraflow Feasibility Study 2002 - Evaluate the feasibility of a bus transit contra flow facility in Miami-Dade County, and select and recommend a specific highway or highway corridor for further study and implementation. Completed in 2002. Work by Kimley-Horn & Associates. Download the Executive Summary and Final Report. Contact Jesus Guerra at 305-375-4507 for complete details.

  37. Transit Corridors Transitional Study 1994 - This study compared the costs, revenues, ridership, and benefits between the Northeast, North, West, Kendall, Homestead, and Miami Beach transit corridors. No priorities were derived from the study. Please visit our office to view or receive a copy of this report. Contact Larry Foutz at 305-375-4507 for complete details.

  38. Transit Hub Evaluation Study 2008 - Develop a comprehensive transit hub system plan that will best serve transit patrons and ease of travel. Started April 2008 and completed March 2009. Work by The Corradino Group. The approximate cost was $60,000. Download the Final Report, May 2009. Contact Wilson Fernandez at 305-375-4507 for complete details.

  39. Transit On-Board Survey 2008 - The objective of this study was to develop a data collection program that meets FTA guidelines to support transit modeling efforts. Started October 2008 and completed July 2009. The approximate cost is $150,000. Download the Final Report, July 2009. Contact Larry Foutz at 305-375-4507 for complete details.

  40. Transit Oriented Development Master Plans for Exclusive Busway Corridors Study 2003 - To complete master plans and implementing regulations for two planned Community Urban Centers (CUCs) designated in the Miami-Dade’s Adopted 2005-2015 Land Use Plan along the programmed Exclusive Busway Extension located along US1 at the intersections of SW 216th and 248th streets. The aforementioned will implement the county’s Comprehensive Development Master Plan (CDMP) provisions governing planned CUC and the CDMP Guidelines for Urban Form which seek to promote pedestrian-friendly, mixed-use and transit-supportive development in connection with the Busway. Completed November 2003. Work by Miami-Dade Planning & Zoning. Download the Palmetto Bay Ordinance and Perrine District Ordinance. Contact Susan Schreiber at 305-375-4507 for complete details.

  41. Vanpool Demonstration Program 1996 - Provide vans to individuals traveling together on a regular basis to work, as well as institutions, businesses, agencies and other organizations. This program is a result of the Congestion Mitigation: Public-Private Partnerships Study conducted for the MPO in March 1994. Completed in January 1997. Work by Vanpool Services Incorporated. Please visit our office to view or receive a copy of this report. Contact Jesus Guerra at 305-375-4507 for complete details.

Help (next 3 entries below)

  1. Click here to get our RSS News Feed.
  2. Download helpful viewers: Flash and Acrobat.
  3. Click to send comments, suggestions and questions to the webmaster.

Search our site

Google Custom Search

Mini Sites (next 7 entries below have no text-only versions and open in separate browser windows)

  1. InteracTIP 2010
  2. TIP with Google Maps!
  3. My Neighborhood