Roadway Construction Report
Week of April 10 - 16, 2017

MIAMI (April 07, 2017)

The following is a list of roadway construction/closure activities for the week of April 10 - 16, 2017.

  • Old Cutler Rd. from SW 63rd Ave. to Cartagena Plaza – Project No. 20130278:
    This project consists of, but is not limited to, reconstruction, widening the bicycle route a minimum of 8 feet wide and relocating it further away from traffic lanes where possible; curb and gutters; installing remedial drainage as necessary; resurfacing segments that are to remain; pruning trees and tree roots; installing root barriers to prevent future damage; and installing regulatory signage for bicycles and pedestrians. Construction is anticipated to be completed by May 2017. Mainline Closure: Motorists are advised to follow the posted maintenance of traffic (MOT) signs or detour route.

  • SW 264th St. from SW 137th Ave. to U.S. 1 – Project No. 20140229:
    Work under this contract includes, but is not limited to, the widening of the existing roadway to a two-lane divided highway with raised landscaped median, bike lanes, on-street parking, sidewalks, curb and gutter, a continuous storm drain system, signalization, pavement markings and signage, and street lighting. Construction is anticipated to be completed by May 2017. Mainline Closure: Motorists are advised to follow the posted maintenance of traffic (MOT) signs or detour route.

  • NW 74th St. from NW 107th Ave. to NW 114th Ave. – Project No. 20120004:
    Work includes improvement and widening to the existing road from a five-lane undivided roadway to a six-lane divided roadway, reducing the width of the existing median to accommodate a bicycle facility, sidewalks, curb and gutters, a continuous storm drainage system, pavement markings and signage, traffic signalization, roadway lighting, sound barrier walls on both sides of the roadway, landscaping, and irrigation. Construction is anticipated to be completed by April 2017. Mainline Closure: Motorists are advised to follow the maintenance of traffic (MOT) signs or detour route.

  • Tamiami Canal Bridge Replacement – Project No. 20140081:
    The project consists of replacing the historic swing bridge currently spanning the Tamiami Canal along NW South River Drive with a bascule bridge, which will include bicycle and pedestrian facilities. During the project, NW South River Drive will be closed to vehicular, pedestrian and cyclist traffic between NW 20th Street and NW 32dn Avenue. Access to local business will be maintained. Construction is anticipated to be completed by February 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • NE 197 St. & 24 Ave. - Project No. 20150079, WO # 7:
    Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by April 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • SW 127 to 128 Ave., from 58 LN to 65 St. – Project No. 20150079, WO # 8:
    Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by April 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • NW 112 Ave. from NW 103 St. to NW 106 St. and NW 108 Ave. from NW 103 St. to NW 106 St. – Project No. 20160040, WO # 4:
    Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by May 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • East Venetian Causeway Bridges Rehabilitation (874474 & 8744781) Project No. 20160090:
    The Venetian East Bascule Bridge was open to traffic on Dec. 28, 2016.  Additionally, rehabilitation work activities are still ongoing at the Purdy Avenue Bridge (fixed bridge). This work is scheduled to be completed by April 2017.  Motorists are advised to follow the posted maintenance of traffic (MOT) signs.

  • SW 152nd Street from SW 147th Avenue to SW 157th Avenue - Project No. 20150187:
    The work consists of widening the existing roadway from two (2) to four (4) lanes with a raised median, sidewalks, curb and gutters, bicycle paths, a continuous storm drainage system, signalization, pavement markings and signage, and decorative lighting. Construction is anticipated to be completed by April 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • W 12 Ave. from W 41 St. to W 60 St. – Project No. 20150132 – WO # 3:
    The scope of work includes the following:milling and resurfacing, construction of ADA ramps and connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by May 2017. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • NW 173rd Dr. from NW 68th Ave. to NW 72nd Ave. – Project No. 20160222 –
    WO # 5:
    Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by December 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • NE 209th Terr. And NE 214th St. from NE 24th Ct. to NE 25th Ct. – Project No. 20150218:
    The scope of work includes the following:  Work includes extending several culverts by slip lining them with pipe, backfilling over the extended culverts with suitable material, and adding new sidewalk segments to connect existing sidewalks along residential roads that currently pass over the Oleta River.  This work will enhance the safety of the roadway and make it more pedestrian friendly. Construction is anticipated to be completed by July 2017. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • SW 16 St. to SW 24 St. and SW 82 Ave. to SW 87 Ave. – Project No. 20150156 – WO # 5:
    The scope of work includes the following: milling and resurfacing, construction of ADA ramps and connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by June 2017. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • West Dixie Highway from NE 203 St. to NE 215 St. L – Project No. 20160019 – WO # 5:
    The scope of work includes the following: milling and resurfacing, construction of ADA ramps and connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by June 2017. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • West Dixie Highway from NE 174 St. to NE 186 St. – Project No. 20150061 – WO # 5:
    The scope of work includes the following: milling and resurfacing, construction of ADA ramps and connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by May 2017. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • NE 191st Street from NE 18th Avenue to NE 14th Avenue. Project – 20150217 – WO #4:
    Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by August 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • NW 88th St. from NW 24th Ave. to NW 25th Ave. – Project No. 20160222 – WO # 4:
    Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by April 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • SW 80th St. from SW 149th Ave. to SW 154th Ave. Project No. 20160195:
    Work includes, but is not limited to, the construction and installation of, drainage structures, French drains, miscellaneous drainage improvements, swale blocks, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by August 2017. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • West Dixie Highway from NE 186 St. to NE 193 St. – Project No. 20150061 – WO # 6:
    The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by June 2017. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

  • SW 142nd Ave. from SW 26th St. to SW 8th St. Project No. 20160232:
    Work under this contract includes, but is not limited to the reconstruction and widening of the existing roadway from two lanes to three lanes, sidewalks, curb and gutters, remedial storm drainage, pavement markings and signage; construction of two circles at SW 14th St. and SW 18th St., improvements of the existing traffic signals and street lighting. Construction is anticipated to be completed by June 2018. Mainline Closure: Motorists are advised to follow the maintenance of traffic (MOT) signs or detour route.

PLEASE DON'T TEXT AND DRIVE!

Please advise us if you wish for your name to be removed from this distribution list. Thank you. All information listed above is subject to change if the respective contractor's schedule is altered due to unforeseen circumstances.