Roadway Construction Report for the Week of January 1-7, 2018

MIAMI (December 29, 2017)

The following is a list of roadway construction/closure activities for the week of January 1-7, 2018.

Tamiami Canal Bridge Replacement – Project No. 20140081: The project consists of replacing the historic swing bridge currently spanning the Tamiami Canal along NW South River Drive with a bascule bridge, which will include bicycle and pedestrian facilities. During the project, NW South River Drive will be closed to vehicular, pedestrian and cyclist traffic between NW 20th Street and NW 32nd Avenue. Access to local business will be maintained. Construction is anticipated to be completed by February 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 152nd St. from SW 147th Ave. to SW 157th Ave. - Project No. 20150187: The work consists of widening the existing roadway from two (2) to four (4) lanes with a raised median, sidewalks, curb and gutters, bicycle paths, a continuous storm drainage system, signalization, pavement markings and signage, and decorative lighting. Construction is anticipated to be completed by April 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 142nd Ave. from SW 26th St. to SW 8th St. Project No. 20160232: Work under this contract includes, but is not limited to the reconstruction and widening of the existing roadway from two lanes to three lanes, sidewalks, curb and gutters, remedial storm drainage, pavement markings and signage; construction of two circles at SW 14th St. and SW 18th St., improvements of the existing traffic signals and street lighting. Construction is anticipated to be completed by June 2018. Mainline Closure: Motorists are advised to follow the maintenance of traffic (MOT) signs or detour route.

NE 16th Ave. from NE 123rd St. to NE 135th St. Project No: 20160278: Work under this contract includes, but is not limited to, the widening of the existing roadway from two lanes to three lanes, bike lanes, sidewalks, curb and gutter, a continuous storm drain system, pavement markings and signage, improvements to the existing traffic signals, and decorative street lighting. Construction is anticipated to be completed by June 2018. Mainline Closure: Motorists are advised to follow the maintenance of traffic (MOT) signs or detour route.

NE 2nd Ave. from NE 69th St. to NE 84th St. – Project No. 20150169: This work includes but is not limited to roadway reconstruction, installation of a new stormwater system, sidewalks, curb and gutters, pavement markings, signage, signalization, decorative lighting, landscaping, a 12-inch water main and all appurtenances on NE 2 Avenue, from NE 79 Street to NE 84 Street. Construction is anticipated to be completed by June 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 22nd Ave. from NE 202nd St. to NE 199th St. – Project No. 20160325: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by January 2018. Mainline Closure: Detour Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 127th Ct. to SW 129th PL and SW 110th Terr. to SW 112th St. – Project No.20160020 – WO #5: The scope of work includes the following: milling and resurfacing, construction of ADA ramps and connectors, adjustment of valves boxes and manholes, pavement marking and signage. Construction is anticipated to be completed by January 2018. Detour: Motorist are advised to seek an alternate route or follow the posted maintenance (MOT) signs or detour route.

NW 12th Ave. from NW 54th St. to NW 62nd St. – Project No. 20160020 – WO #6: The scope of work includes the following: milling and resurfacing, construction of ADA ramps and connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 12th Ave. from NW 40th St. to NW 46th St. – Project No. 20150157 – WO #7: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 202nd St. from NE 21st Ave. to Highland Lakes Blvd. – Project No. 20160325 - WO #2: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by January 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 12th Ave. from NW 46th St. to NW 54th St. – Project No. 20160266 – WO #3: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 42nd St. and SW 154th Ct. – Project No. 20160290 - WO #4: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by January 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 95 St. to NW 103 St. and NW 32 Ave. to NW 37 Ave. – Project No. 20170005 – WO #1: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by March 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 67th Ave. and SW 57th Terr. – Project No. 201760333- WO #4: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by January 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 2nd Ave. from NW 86th St. to NW 91st Street & NW 2nd Ave. from NW 111th St. to NW 119th St.– Project No. 20160266– WO #4: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by February 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 104 St. and SW 147 Ave. – Project No. 20160143 - WO #5: The improvement at the location includes clearing and grubbing; trees removal; drainage installation; widening; excavation; base installation; milling and resurfacing; installation of concrete curb and gutter; sidewalks and ramp connectors; sodding; signage and pavement markings installation, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by April 2018.

NW 132nd PL. from NW 8th Terr. to NW 9th Terr. – Project No. 20160290- WO #5: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by January, 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 187th Ave. from SW 296th St. to SW 312th St. – Project No. 20160345 – WO #3: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 104 St. and Hammocks Blvd. – Project No. 20170024 - WO #1: The improvement at the location includes clearing and grubbing; trees removal; drainage installation; widening; excavation; base installation; milling and resurfacing; installation of concrete curb and gutter; sidewalks and ramp connectors; sodding; signage and pavement markings installation, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by June 2018.

NE 24th Court from NE 209th Terrace to NE 215th Street – Project No. 20170108: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by April 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 89th Street and NE 90th Street from NE 10th Court to N. Bayshore Drive – Project No. 20170147: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by June 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route. 