Roadway Construction Report for the week of October 15-21, 2018

MIAMI ( October 12, 2018 )

The following is a list of roadway construction/closure activities for the week of October 15-21, 2018.

Tamiami Canal Bridge Replacement – Project No. 20140081: The project consists of replacing the historic swing bridge currently spanning the Tamiami Canal along NW South River Drive with a bascule bridge, which will include bicycle and pedestrian facilities. During the project, NW South River Drive will be closed to vehicular, pedestrian and cyclist traffic between NW 20th Street and NW 32nd Avenue. Access to local business will be maintained. Construction is anticipated to be completed by Fall 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 16th Ave. from NE 123rd St. to NE 135th St. – Project No: 20160278: Work under this contract includes, but is not limited to, the widening of the existing roadway from two lanes to three lanes, bike lanes, sidewalks, curb and gutter, a continuous storm drain system, pavement markings and signage, improvements to the existing traffic signals, and decorative street lighting. Construction is anticipated to be completed by December 2018. Mainline Closure: Motorists are advised to follow the maintenance of traffic (MOT) signs or detour route. 

NE 2nd Ave. from NE 69th St. to NE 84th St. – Project No. 20150195:  This work includes but is not limited to roadway reconstruction, installation of a new stormwater system, sidewalks, curb and gutters, pavement markings, signage, signalization, decorative lighting, landscaping, a 12-inch water main and all appurtenances on NE 2nd Avenue, from NE 79th Street to NE 84th Street. Construction is anticipated to be completed by December 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 89th St. and NE 90th St. from NE 10th Ct. to N. Bayshore Dr. – Project No. 20170147: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by December 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 328th St. from US 1 to SW 167th Ave. – Project No. 20150169: Work includes widening the existing roadway from two (2) to four (4) lanes with a raised median, sidewalks, curb and gutter, bicycles facilities, continuous storm drainage system, signalization, pavement markings and signage and decorative lightning. Construction is anticipated to be completed by January 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

Blue Lagoon Drive from NW 57th Ave. to NW 62nd Ave.   –  Project No. 20170259:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by February 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 248th St. from SW 147th Ave. to SW 177th Ave. – Project No. 20170254 – WO # 3: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by November 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 157th Ave. from SW 64th St. to SW 72nd St. – Project No. 20170165 – WO # 5: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by October 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 232nd St. from US-1 to SW 167th Ave. – Project No. 20170279 WO # 1: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by November 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 25th Ave. from NE 188th St. to NE 191st St.   –  Project No. 20170237 W.O. # 2: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by March 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 79th Ave. from W Flagler St. to NW 7th St. – Project No. 20170005 – WO # 4:  The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by October 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 34th Ave. from NW 101st St. to NW 102nd St. – Project No. 20170025 - WO # 5: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by October, 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

Ron Ehmann Park SW 112th St. from SW 95th Ave. to SW 97th Ave. – Project No. 20170202: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by February 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 87th Ave. from NW 186th St. to NW 189th St. – Project No. 20170319-R WO # 1: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by October 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 199th St from NE 14th Ave. to NE 15th Ct. – W.O. # 3. Project No. 20170317: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by October 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

W 68 ST from W 4 Ave. to W 12 Ave. – Project No. 20170253 – WO # 4: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 184 St. from SW 112 Ave. to US-1– Project No. 20170024 - WO # 5: The improvement at the location includes clearing and grubbing, construction of concrete medians, signage, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by November 2018.

NW 35 Ave. from NW 96 St. to NW 97 St. – Project No. 20170025 - WO # 6: The improvement at the location includes clearing and grubbing; drainage installation, milling and resurfacing, signage and pavement markings installation, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by December 2018.

W 68 St. from W 12 Ave. to W 17 Ct. (Phase 2) – Project No. 20170253 – WO # 5:  The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

 