Roadway Construction Report for the week of November 19-25, 2018

MIAMI ( November 16, 2018 )

The following is a list of roadway construction/closure activities for the week of  November 19-25, 2018.

NE 16th Ave. from NE 123rd St. to NE 135th St. – Project No. 20160278: Work under this contract includes, but is not limited to, the widening of the existing roadway from two lanes to three lanes, bike lanes, sidewalks, curb and gutter, a continuous storm drain system, pavement markings and signage, improvements to the existing traffic signals, and decorative street lighting. Construction is anticipated to be completed by December 2018. Mainline Closure: Motorists are advised to follow the maintenance of traffic (MOT) signs or detour route.

NE 2nd Ave. from NE 69th St. to NE 84th St. – Project No. 20150195:  This work includes but is not limited to roadway reconstruction, installation of a new stormwater system, sidewalks, curb and gutters, pavement markings, signage, signalization, decorative lighting, landscaping, a 12-inch water main and all appurtenances on NE 2nd Avenue, from NE 79th Street to NE 84th Street. Construction is anticipated to be completed by December 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 89th St. and NE 90th St. from NE 10th Ct. to N. Bayshore Dr. – Project No. 20170147: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by December 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 328th St. from US 1 to SW 167th Ave. – Project No. 20150169: Work includes widening the existing roadway from two (2) to four (4) lanes with a raised median, sidewalks, curb and gutter, bicycles facilities, continuous storm drainage system, signalization, pavement markings and signage and decorative lightning. Construction is anticipated to be completed by January 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

Blue Lagoon Drive from NW 57th Ave. to NW 62nd Ave.  – Project No. 20170259:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by February 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

Ron Ehmann Park SW 112th St. from SW 95th Ave. to SW 97th Ave. – Project No. 20170202: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by February 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 87th Ave. from NW 186th St. to NW 189th St. – Project No. 20170319-R WO # 1: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by November 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

W 68 St. from W 4 Ave. to W 12 Ave. – Project No. 20170253 WO # 4: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 184 St. from SW 112 Ave. to US-1– Project No. 20170024 WO # 5: The improvement at the location includes clearing and grubbing, construction of concrete medians, signage, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by November 2018.

W 68 St. from W 12 Ave. to W 17 Ct. (Phase 2) – Project No. 20170253 WO # 5:  The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by January 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route. 

Rana Park NW 133rd St. to NW 132nd Terr. from NW 13th Ave. to NW 16th Ave. – Project No. 20170317 WO # 4: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by December 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

Homestead Ave. from SW 181st Terr. to SW 184th St. – Project No. 20170254 WO # 4: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by December 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.  

SW 147th Ave. from SW 104th St. to SW 120th St.– Project No. 20170279 WO # 3:The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by March, 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 158th St. and NW 22nd Ave. –  Project No. 20170319-R WO # 4: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by November 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 56th St. from SW 72nd Ave. to SW 75th Ave. – Project No. 20180049 WO # 1: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by February 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.  

NW 108th Ct. from West Flagler Street to NW 1st Lane – Project No. 20170237 WO # 1:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by November 2018. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

N Miami Ave. from N 29th St. to N 36th St. and from N 20th St. to N 22nd St. – Project No. 20170279 WO # 5: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by December 2018. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 58th St. and NW 117th Ave. – Project No. 20160301: The scope of work consists of, but is not limited to, improvements to the flood control structure including new headwalls, operator pad, motorized gates, extension of existing culverts, and integration of the motor controls into the SCADA system, which will allow for remote monitoring, automated and remote control of said structure. This project will provide better water management and will increase the level of service being provided to public and private residents within the Dressels Canal Basin. Construction is anticipated to be completed by February 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

 