Roadway Construction Report for the week of May 6 -12 2019

MIAMI ( May 03, 2019 )

The following is a list of roadway construction/closure activities for the week of May 6-12, 2019.

SW 328 St. from US 1 to SW 167 Ave. – Project No. 20150169: Work includes widening the existing roadway from two (2) to four (4) lanes with a raised median, sidewalks, curb and gutter, bicycles facilities, continuous storm drainage system, signalization, pavement markings and signage and decorative lightning. Construction is anticipated to be completed by August 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 152 Terr. to SW 154 Street, from SW 99 Ct. to SW 100 Ave. – Project No. 20180108 WO #1: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by May 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 57 Ave. (Curtiss Parkway) from NW 36 St. to South of Circle – Project No. 20180048 WO #1: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by June 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 107 Ave. from NW 41 St. to NW 58 St. – Project No. 20180049 WO #3: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by June, 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

6725 SW 125 Ave. and 6255 SW 125 Ave. – Project No. 20170024 WO #8: The improvement includes construction of Two Traffic Calming Devices (Speed Humps) at these locations to improve the traffic safety along SW 125 Avenue; also includes; signage; pavement markings installation and sodding, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by May 2019.

SW 149 Ave. and SW 26 St. – Project No. 20170024 – WO #7: The improvement at the location includes trees removal, clearing and grubbing, removal and construction of curb, gutter, sidewalks and ramps, drainage installation, road widening, milling and resurfacing, signage, pavement markings installation, sodding, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by May 2019.

William Powell Bridge Expansion Joint and Fender System Rehabilitation-Project No. 20180090: Work includes but is not limited to replacement of the William Powell expansion joints, restored concrete spall areas, crack injection in bridge concrete elements, replacement of navigation bridge fender system and navigations lights. Construction is anticipated to be completed by December 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 175 St. from NW 42 Ave. to NW 32 Ave. and NW 175 St. and NW 37 Ave. (Intersection) – Project No. 20170253 – WO #8: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by June 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 264 St. and SW 157 Ave. – Project No. 20170165 – WO #7: The scope of work includes the following: milling and resurfacing, pavement markings and signage. Construction is anticipated to be completed by June 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 175 St. from NW 12 Ave. to NW 22 Ave. – Project No. 20170253 – WO #9: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by July 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 175 St. from NW 32 Ave. to NW 22 Ave. – Project No. 20170280 – WO #7: The scope of work includes the following: milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by July 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 72 St. and SW 152 Ave. – Project No. 20170024 – WO #6: The improvement at the location includes trees removal, clearing and grubbing, removal and construction of curb and gutter, road widening, milling and resurfacing, signage, pavement markings installation and sodding, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by May 2019.

SW 184 St. from Florida Turnpike to SW 115 Ave. and SW 184 St. from SW 122 Ave. to SW 123 Ave. – Project No. 20170165 – WO #8: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by July 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 147 Ave. from SW 88 St. to SW 104 St. – Project No. 20180049 – WO #4: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by August 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 41 St. from FL Turnpike to Vulcan Entrance (NW 127 Ave.) – Project No.20180048 – WO #4: The scope of work includes the following:  Milling and resurfacing, adjustment of valve boxes and manholes and pavement markings. Construction is anticipated to be completed by June 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 93 Ct. from SW 51 St. to SW 48 St. –Project No. 20180108 WO #2: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by July 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 102 St. and NW 7 Ave. – Project No. 20170319-R WO #7:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by July 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 41 St. from Vulcan Entrance (NW 127th Ave.) to Dead End – Project No. 20180048 WO #5: The scope of work includes milling, resurfacing, and pavement markings. Construction is anticipated to be completed by July 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

West Park Dr. and NW 7 St. (Fontainebleau Blvd) -Project No. 20180074 – WO #6: New Traffic Signal Installation work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly , ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. This work began in April 2019 and is anticipated to be completed by August 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 117 Ave. and SW 248 St. - Project No. 20180075 WO #1: New Traffic Signal Installation work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly , ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. This work began in March 2019 and is anticipated to be completed by July 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 37 Ave. and Poinciana Ave. - Project No. 20180075 WO #2: New Traffic Signal Installation work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly , ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. This work began in March 2019 and is anticipated to be completed by July 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

 

 