Roadway Construction Report for the week of July 8 - 14, 2019

MIAMI ( July 05, 2019 )

The following is a list of roadway construction/closure activities for the week of July 8-14, 2019.

SW 328 St. from US 1 to SW 167 Ave. – Project No. 20150169: Work includes widening the existing roadway from two (2) to four (4) lanes with a raised median, sidewalks, curb and gutter, bicycles facilities, continuous storm drainage system, signalization, pavement markings and signage and decorative lightning. Construction is anticipated to be completed by August 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

William Powell Bridge Expansion Joint and Fender System Rehabilitation-Project No. 20180090: Work includes but is not limited to replacement of the William Powell expansion joints, restored concrete spall areas, crack injection in bridge concrete elements, replacement of navigation bridge fender system and navigations lights. Construction is anticipated to be completed by December 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 112 St. from SW 122 Ave. to SW 137 Ave. – Project No. 20180049 WO #5: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by August 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 157 Ave. from SW 88 St. to SW 104 St. – Project No. 20180177 – WO #1:  The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by September 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 194 Ave. from SW 208 St. to SW 216 St. – Project No. 20180049 – WO #6: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by September 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 104 St. from SW 157 Ave. to SW 167 Ave. – Project No. 20180252 – WO #1: The scope of work includes the following:  milling and resurfacing, construction of ADA   Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by September 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 87 Ave. and SW 134 St. - Project No. 20180136 WO #1:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by July 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 24 Ave. from NW 77 Terr. to NW 79 St. –Project No. 20180216 WO #1: Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications.. Construction is anticipated to be completed by July 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NE 147 St. from West Dixie Hwy to NE 18 Ave. – Project No. 20180108 WO #5:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by July 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 128 St. and SW 107 Ave. – Project No. 20170024 - WO #10: The improvement includes construction of Traffic Calming Device (Traffic Circle) at this location to improve the traffic flow and safety at the mentioned intersection. The project also includes drainage installation, milling and resurfacing, signage, pavement markings installation and sodding, as well as any ancillary items associated with the project scope of work. Construction is anticipated to be completed by September 2019

NW 21 Ave. and NW 71 St. – Project No. 20180216 WO #2:  Work includes, but is not limited to, the construction and installation of drainage structures, French drains, miscellaneous drainage improvements, grading, sodding, and roadway restoration, including construction of concrete curb and gutters, and sidewalks where needed, in accordance with the construction plans and specifications. Construction is anticipated to be completed by July 2019. Mainline Closure: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 25 St. east crosswalk of NW 107 Ave. to Approximately 800 ft. to the east   – Project No. 20170254 WO # 9: The scope of work includes the following:  milling and resurfacing, construction of ADA Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by September 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 211 St. from Florida Turnpike Exp. to US-1   – Project No. 20180253 WO # 2: The scope of work includes the following:  milling and resurfacing, construction of ADA   Ramps and Connectors, adjustment of valve boxes and manholes, pavement markings and signage. Construction is anticipated to be completed by November 2019. Detour: Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

West Park Dr. and NW 7 St. (Fontainebleau Blvd) - Project No. 20180074 WO #6: New Traffic Signal Installation; Work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly , ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. Project began in April 2019 and is anticipated to be completed by August 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 117 Ave. and SW 248 St. - Project No. 20180075 WO #1: New Traffic Signal Installation; Work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly, ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. Project began in March 2019 and is anticipated to be completed by July 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

SW 97 Ave. and SW 28 St. - Project No. 20180075 WO #9: New Traffic Signal Installation; Work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly , ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. Project began in May 2019 and is anticipated to be completed by November 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

NW 127 Av and NW 2 St. Project No. 20180074 WO #10: New Traffic Signal Installation; Work includes, but is not limited to, the construction and installation of mast arms assemblies, traffic controller, assembly, ground electrodes, conduits, pull boxes, foundations, pedestrian signal heads with push buttons and signs, overhead signs, traffic signal heads, internally illuminated street name signs, loop assemblies, signal cables, milling and resurfacing and any ancillary work including milling and resurfacing, handicap ramps, ground mounted signs, pavement markings, construction of sidewalks, curb and gutter. Project began in June 2019 and is anticipated to be completed by November 2019. Motorists are advised to seek an alternate route or follow the posted maintenance of traffic (MOT) signs or detour route.

 