The total project budget, excluding FDOT’s construction items, is $526 million Year of Expenditure (YOE).
-
Third quarter 2008 - All right-of-way acquisition is scheduled to be completed.
-
March 2008 - Florida AT&T relocation began along NW 41st Street from NW 22nd Court to NW 24th Avenue, from NW 36th Street to NW 28th Street and NW 33rd Avenue to NW 37th Avenue.
-
January 2008 - Final Design was completed.
-
January 2008 - Florida City Gas began utility relocation along both the north and south sides of NW 41st Street from NW 22nd Court to NW 32nd Avenue.
-
January 2008 - Florida Power and Light (FPL) distributtion relocation began.
-
December 2007 - A notice to proceed (NTP) was issued to FPL Transmission.
-
April 2006 - A Value Engineering (VE) Workshop was held.
-
April 2006 - The United States Coast Guard issued a Finding of No Significant Impact (FONSI) and an Environmental Assessment (EA).
-
October 2004 - The decision was made to implement this project with 100% state and local funds. MDT has entered a Joint Participation Agreement (JPA) with the Florida Department of Transportation (FDOT) that will fund up to $100 million of the project costs. The balance of the project cost will be paid for by utilizing proceeds from the half-penny sales surtax.
-
September 2003 - The Locally Preferred Alternative (LPA) for the MIC/Earlington Heights Connector project was approved by the Metropolitan Planning Organization (MPO), and in March 2006, the revised LPA was approved by the MPO.