File Number: 261136 File Type: Resolution Status: In Committee
Version: 0 Reference: Control: Transportation Cmte
File Name: OFF-SYSTEM AGREEMENT FOR LOCAL ROADWAY IMPROVEMENTS Introduced: 6/22/2026
Requester: Transportation and Public Works Cost: Final Action:
Agenda Date: 9/1/2026 Agenda Item Number: 8N
Notes: Title: RESOLUTION APPROVING AN OFF-SYSTEM CONSTRUCTION AND MAINTENANCE AGREEMENT BETWEEN MIAMI-DADE COUNTY AND THE FLORIDA DEPARTMENT OF TRANSPORTATION FOR LOCAL ROADWAY IMPROVEMENTS FOR SR 934/NW 74TH STREET CONNECTOR FROM WEST OF NW 77TH COURT TO EAST OF RED ROAD, A PORTION OF THE PROJECT INCLUDES WORK ON NW 74TH STREET CONNECTOR AND NW 72ND AVENUE, IN MIAMI-DADE COUNTY, FLORIDA; AND AUTHORIZING THE COUNTY MAYOR OR COUNTY MAYOR’S DESIGNEE TO EXECUTE THE SAME AND EXERCISE THE PROVISIONS CONTAINED THEREIN
Indexes: NONE
Sponsors: NONE
Sunset Provision: No Effective Date: Expiration Date:
Registered Lobbyist: None Listed


Legislative History

Acting Body Date Agenda Item Action Sent To Due Date Returned Pass/Fail

County Attorney 6/24/2026 Assigned Dale P. Clarke 6/17/2026

ROY COLEY 6/22/2026 Assigned Office of Agenda Coordination

Office of Agenda Coordination 6/22/2026 Assigned County Attorney 9/1/2026
REPORT: DTPW - Annery Pulgar Alfonso - no sponsor - pending July cmte - Attachment: Agreement - item has 21 pages

Legislative Text


TITLE
RESOLUTION APPROVING AN OFF-SYSTEM CONSTRUCTION AND MAINTENANCE AGREEMENT BETWEEN MIAMI-DADE COUNTY AND THE FLORIDA DEPARTMENT OF TRANSPORTATION FOR LOCAL ROADWAY IMPROVEMENTS FOR SR 934/NW 74TH STREET CONNECTOR FROM WEST OF NW 77TH COURT TO EAST OF RED ROAD, A PORTION OF THE PROJECT INCLUDES WORK ON NW 74TH STREET CONNECTOR AND NW 72ND AVENUE, IN MIAMI-DADE COUNTY, FLORIDA; AND AUTHORIZING THE COUNTY MAYOR OR COUNTY MAYOR�S DESIGNEE TO EXECUTE THE SAME AND EXERCISE THE PROVISIONS CONTAINED THEREIN

HEADER
WHEREAS, this Board desires to accomplish the purposes outlined in the accompanying memorandum, a copy of which is incorporated herein by reference,

NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF MIAMI-DADE COUNTY, FLORIDA, that this Board:

Section 1. Approves the Off-System Construction and Maintenance Agreement between Miami-Dade County and the Florida Department of Transportation, in substantially the form attached hereto and incorporated herein, for the implementation of local roadway improvements within Project No. FM452566-1-52-01, SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. A portion of the project includes work on NW 74th Street Connector and NW 72nd Avenue, in Miami-Dade County, Florida.

Section 2. Authorizes the County Mayor or County Mayor�s designee to execute the agreement for and on behalf of Miami-Dade County and to exercise the provisions contained therein.

HEADER
Date:

To: Honorable Chairman Anthony Rodriguez
and Members, Board of County Commissioners

From: Daniella Levine Cava
Mayor

Subject: Off-System Construction and Maintenance Agreement with State of Florida, Department of Transportation and Miami-Dade County for Local Roadway Improvements for SR 934/NW 74th Street Connector from West of NW 77th Court to East of Red Road

STAFF RECOMMENDATION
Executive Summary
The purpose of this item is for the Board of County Commissioners (Board) to approve an Off-System Construction and Maintenance Agreement with the Florida Department of Transportation (FDOT) for the implementation of local roadway improvements within Project No. FM452566-1-52-01, i.e., SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. A portion of the project includes work on NW 74th Street Connector and NW 72nd Avenue, roads not on the State Highway System.

Some of the specific local improvements include the reconstruction of existing sidewalks, curb ramps, and a traffic separator. The project is estimated to cost $5,900,000 and will be funded and built by FDOT. The anticipated construction start date is March 2027.

Recommendation
It is recommended that the Board approve the attached resolution authorizing the execution of an Off-System Construction and Maintenance Agreement between the County and FDOT for local roadway improvements within Project No. FM452566-1-52-01, i.e., SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road. The estimated project cost is $5,900,000 and will be funded by FDOT.

Scope
The project is in Districts 6 and 12, which are represented by Commissioner Natalie Milian Orbis and Commissioner Juan Carlos Bermudez, respectively.

Delegation of Authority
The authority of the County Mayor or County Mayor's designee to execute and implement this agreement, including exercising all the provisions contained therein, is consistent with those authorities granted under the Code of Miami-Dade County.

Fiscal Impact/Funding Source
The project is estimated to cost $5,900,000 and will be funded and built by FDOT. The County is required to provide maintenance operations within the County�s right-of-way upon completion of the project. The County�s maintenance costs are funded through DTPW�s General Fund allocation.

Track Record/Monitor
DTPW is the entity overseeing this project and the person responsible for monitoring it is Maria D. Molina P.E., Chief, Right-of-Way and Stormwater Planning and Design Division.

Background
This Off-System Construction and Maintenance Agreement is for the construction of local improvements for SR 934/NW 74th Street Connector from west of NW 77th Court to east of Red Road, specifically at the intersection at NW 74th Street Connector and NW 72nd Avenue. The improvements consist of the following:

� Curb ramps
� Sidewalk
� Curb and gutter
� Milling and resurfacing
� Widening
� Striping
� Traffic separator
� Loops
� Signage

If the project requires the acquisition of additional right-of-way, FDOT shall acquire such right-of-way to complete the project at no cost to the County. The anticipated construction start date is March 2027.



_________________________
Roy Coley
Deputy Mayor








Home  |   Agendas  |   Minutes  |   Legislative Search  |   Lobbyist Registration  |   Legislative Reports
2026 BCC Meeting Calendar  |   Miami-Dade County Code of Ordinances   |   ADA Notice  |  

Home  |  Using Our Site  |  About Phone Directory  |  Privacy  |  Disclaimer

E-mail your comments, questions and suggestions to Webmaster  

Web Site � 2026 Miami-Dade County.
All rights reserved.