This work involves disconnecting existing water meters from the service water lines located at
the rear or side of the properties and connecting new water service lines of the residences to the
existing water meter at the front of the property, as shown on the attached sketch in the
appendices.
The Contractor shall meet the property owners/tenants where the conversion will be performed,
and the property owner shall have the opportunity to review the proposed route and provide
their input. The contractor shall obtain the owner's signature for all required permits and shall be
responsible for applying for and obtaining the required permits, including preparing the
plumbing/electric permit application, pulling plumbing/electric permits, and any other required
permits from the Building Office of the municipality in which the work is to be performed.
LICENSES REQUIRED:
License Requirements
At the time of Bid and according to the requirements of Section 10-3 of the Code of Miami-Dade
County, Florida, and these Solicitation and Contract Documents, the Bidder must hold a valid,
current, and active: i. Certificate of Competency from the County's Construction Trades Qualifying
Board as a General Contractor or Plumbing. or ii. Certification, as a General Contractor or
Plumbing Contractor, provided by the State of Florida Construction Industry Licensing Board,
according to the provisions of Florida Statutes Chapter 489.115.
MINIMUM EXPERIENCE REQUIRED:
1. The Bidder must demonstrate that it has full-time personnel with the necessary
experience to perform the Project’s Scope of Work. The Bidder shall provide a list of no
less than three (3) references who can confirm that the bidder has completed projects
performed by the identified personnel, the bulk of whose work performed on the private
property is similar in detail to the Project’s Scope of Work described in these Solicitation
Documents. Each reference shall include the following: the contact’s name, telephone
2. number, e-mail address, and location where the work was performed.
The experience of key senior personnel with other firms may be counted toward the
experience requirement, if acceptable to the Department. Should such evidence not be
satisfactory to the Department, whose decision shall be final.
3. 4. In the event a firm is established by executives, supervisors, and other senior field staff
(key employees) that would have met these minimum experience requirements with a
prior firm, the Department reserves the right to qualify the firm based on the
Department's sole determination and evaluation of the knowledge and previous
experience of these key employees employed by the new firm. The experience of key
senior personnel with other firms may be counted towards the experience requirement, if
acceptable to the department. Should such evidence not be satisfactory to the
Department, whose decision shall be final, the bid will be considered non-responsive, and
the second-lowest bidder will be considered for award. The qualifying proof shall be
submitted in a separate sealed envelope with the bid.
The Contractor must submit proof that his/her firm has the ability to interface with MD-
WASD and familiarity with County guidelines. The ability will be based on the evaluation
of the Company by “Past e-Builder No.20382 Page 4 of 46 Performance Evaluations” (PPE)
from the Miami-Dade County approach, including experience in water service relocation
projects on private properties under WASD’s contracts.
5. The County reserves the right to request additional information and/or contact listed
persons about the bidder's experience.
In the event a firm is established by executives, supervisors, and other senior field staff (key
employees) that would have met these minimum experience requirements with a prior firm,
OWNER reserves the right to qualify the firm based on OWNER's sole determination and
evaluation of the knowledge and prior experience of these key employees employed by the new
firm. The experience of key senior personnel with other firms may be counted towards the
experience requirement, if acceptable to the ENGINEER. Should such evidence not be satisfactory
to the ENGINEER, whose decision shall be final, the bid will be considered non-responsive, and
the second lowest bidder will be considered for award. The qualifying proof shall be submitted in
a separate sealed envelope with the bid.
Contractor must refer to the Request for Price Quotation (RPQ) and associated project
documents for the detail Scope of Work.
Technical Certification:
General Building Contractor, Master Plumber
Commodities
| Code | Description |
|---|---|
| 91060 | PLUMBING SERVICES |
| 96842 | GENERAL CONSTRUCTION |
Solicitation Package/Addendums
| Type | File Name |
|---|---|
| Package | RPQ_No_P20382.pdf |